10801 N OAKDALE AVE 91311
Certificate Information: 10801 N OAKDALE AVE 91311
- Application / Permit
- 18030-10000-07017
- Plan Check / Job No.
- G18LA00254
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- PROPOSED SITE GRADING FOR FOUR (4) LOT SUBDIVISION PER APPROVED PARCEL MAP LA-2006 1333. CUT = 64,618 CU.YDS; SHRINKAGE = 6,462 CU. YDS. FILL = 58,845 CU. YDS. (BALANCE SITE CONDITION, NO IMPORT OR EXPORT).
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/4/2025
Permit Application Status History
| Submitted | 10/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2018 | FREDERICK WONG |
| Corrections Issued | 10/12/2018 | FREDERICK WONG |
| Plan Check Approved | 1/29/2020 | DAN RYAN EVANGELISTA |
| Issued | 2/13/2020 | LADBS |
| Permit Finaled | 2/3/2025 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 10/15/2018 | RYAN HUDSON |
| Miscellaneous | Cleared | 10/16/2018 | RICK TORRES |
| ZI | Cleared | 10/16/2018 | RICK TORRES |
| Grading Pre-Inspection | Cleared | 3/7/2019 | FREDERICK WONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Permit | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 1/27/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kamboj, Naresh Chander; Lic. No.: C21893 | 12950 MACLAY ST SYLMAR, CA 91342 |
| Engineer | Rana,, Masood Sarwar; Lic. No.: C70659 | 19560 SHADOW RIDGE WY NORTHRIDGE, CA 91326 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/4/2020 | Partial Approval | ALEXANDER ANDREWS |
| Bottom/Toe | 10/23/2020 | No Access for Inspection | ALEXANDER ANDREWS |
| Initial Grading | 10/28/2020 | Approved | ALEXANDER ANDREWS |
| Initial Grading | 5/25/2022 | Approved | BRIAN MILLER |
| SWPPP-Const. Storm Water | 5/25/2022 | Not Required | BRIAN MILLER |
| Excavation | 5/27/2022 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 6/2/2022 | Not Ready for Inspection | LANNY MERRICK |
| SWPPP-Const. Storm Water | 6/2/2022 | Completed | LANNY MERRICK |
| Excavation | 6/17/2022 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 6/22/2022 | Approved | VASIL MIHALEV |
| SWPPP-Const. Storm Water | 6/22/2022 | Completed | VASIL MIHALEV |
| Special/Order Compliance | 3/3/2023 | Corrections Issued | BRIAN MILLER |
| Sub-Drain | 8/15/2023 | Conditional Approval | BRIAN MILLER |
| Approved Compaction Report | 8/25/2023 | Not Ready for Inspection | BRIAN MILLER |
| Sub-Drain | 8/25/2023 | Not Ready for Inspection | BRIAN MILLER |
| Sub-Drain | 8/29/2023 | Not Ready for Inspection | MICHAEL TEMPLE |
| Sub-Drain | 9/5/2023 | Partial Approval | BRIAN MILLER |
| Special/Order Compliance | 9/25/2023 | Partial Inspection | BRIAN MILLER |
| Special/Order Compliance | 10/16/2023 | Corrections Issued | BRIAN MILLER |
| Initial Grading | 10/20/2023 | Approved | BRIAN MILLER |
| Final | 12/26/2024 | Corrections Issued | ROBERT PINA |
| Rough | 12/26/2024 | Approved | ROBERT PINA |
| SUSMP-Std. Urban Storm Water | 12/26/2024 | Approved | ROBERT PINA |
| SWPPP-Const. Storm Water | 12/26/2024 | Completed | ROBERT PINA |
| Approved Compaction Report | 1/17/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 1/29/2025 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/3/2025 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |