11001 N LURLINE AVE 91311
Certificate Information: 11001 N LURLINE AVE 91311
- Application / Permit
- 18030-10000-06963
- Plan Check / Job No.
- G18LA00249
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ROUGH GRADING FOR AN 8 LOT SUBDIVISION VTT-54240. CUT: 3,601 CY FILL: 3,744 CY IMPORT: 143 CY
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/9/2023
Permit Application Status History
| Submitted | 10/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 6/3/2020 | DAN RYAN EVANGELISTA |
| Issued | 6/3/2020 | LADBS |
| Permit Finaled | 2/8/2023 | ALEXANDER HELFER |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2018 | APEKSHYA BAJRACHARYA |
| Tract Map conditions | Cleared | 11/13/2018 | BRIDGETTE WOOTEN |
| Permit | Cleared | 11/30/2018 | MARKOS PEREZ-BRAN |
| Work Adjacent to Public Way | Cleared | 11/30/2018 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 8/7/2019 | ORVAL HERNANDEZ-MARCIAL |
| Stormwater Pollution Mitigatn | Cleared | 8/7/2019 | ORVAL HERNANDEZ-MARCIAL |
| Excavation more than 5-ft deep | Cleared | 4/27/2020 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 4/27/2020 | ALEXANDER ANDREWS |
| Roof/Waste drainage to street | Cleared | 5/26/2020 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 6/3/2020 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | Petke,, Jonathan Hobart; Lic. No.: C67585 | 13 SEQUERO RANCHO SANTA MARGARITA, CA 92688 |
| Geologist | Ruberti,, Rudolph F; Lic. No.: EG1708 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/19/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/4/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/4/2020 | Approved | ALEXANDER ANDREWS |
| Excavation | 11/4/2020 | Partial Approval | ALEXANDER ANDREWS |
| SWPPP-Const. Storm Water | 11/4/2020 | Not Required | ALEXANDER ANDREWS |
| Bottom/Toe | 11/5/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/5/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/6/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/6/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/9/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/9/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 11/10/2020 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 11/12/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/12/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/13/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/13/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/16/2020 | No Access for Inspection | ALEXANDER ANDREWS |
| Excavation | 11/16/2020 | No Access for Inspection | ALEXANDER ANDREWS |
| Bottom/Toe | 11/17/2020 | Partial Approval | ALEXANDER ANDREWS |
| Bottom/Toe | 11/18/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/18/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/19/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/19/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/20/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/20/2020 | Approved | ALEXANDER ANDREWS |
| Excavation | 11/20/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 11/23/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 11/24/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/24/2020 | Approved | ALEXANDER ANDREWS |
| Excavation | 11/24/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 11/25/2020 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 12/1/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 12/1/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/2/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/3/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/9/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/10/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/11/2020 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 12/14/2020 | Partial Approval | ALEXANDER ANDREWS |
| Deputy Grading | 12/14/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Grading | 12/22/2020 | Approved | ALEXANDER ANDREWS |
| Approved Compaction Report | 3/15/2021 | Not Ready for Inspection | BRIAN MILLER |
| Approved Compaction Report | 4/5/2021 | Approved | BRIAN MILLER |
| Bottom/Toe | 2/8/2023 | Approved | ALEXANDER HELFER |
| Final | 2/8/2023 | Permit Finaled | ALEXANDER HELFER |
| Rough | 2/8/2023 | Approved | ALEXANDER HELFER |
| SUSMP-Std. Urban Storm Water | 2/8/2023 | Approved | ALEXANDER HELFER |
| SWPPP-Const. Storm Water | 2/8/2023 | Completed | ALEXANDER HELFER |