210 E LINNIE CL 90291

Certificate Information: 210 E LINNIE CL 90291

Application / Permit
18030-10000-05678
Plan Check / Job No.
B18LA17304
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE (R & R, 285 CY)
Permit Issued
Issued on 2/4/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 12/7/2022

Permit Application Status History

Submitted 8/17/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 DEVIN GORDON
Corrections Issued 9/10/2018 DEVIN GORDON
Quality Review Completed 9/13/2018 DAVID CHANG
Building Plans Picked Up 9/20/2018 APPLICANT
Green Plans Picked Up 9/20/2018 APPLICANT
Plan Check Approved 2/12/2019 DEVIN GORDON
Issued 2/4/2020 LADBS
Permit Finaled 12/6/2022 AL GAMBLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/8/2018 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Engineer Nester, Melvin Russell Jr; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Tucker, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/11/2021 Corrections Issued MATTHEW JENKINS
Initial Grading 4/20/2021 Partial Inspection JONATHAN HOM
Initial Grading 4/22/2021 Approved JONATHAN HOM
Initial Grading 4/26/2021 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 4/27/2021 Partial Approval JONATHAN HOM
Bottom/Toe 5/4/2021 Partial Approval JONATHAN HOM
Bottom/Toe 5/18/2021 Partial Approval JONATHAN HOM
Special/Order Compliance 5/18/2021 Partial Inspection JONATHAN HOM
Bottom/Toe 5/21/2021 Partial Approval MATTHEW JENKINS
Excavation 5/25/2021 Partial Approval JONATHAN HOM
Approved Compaction Report 7/1/2021 Approved MATTHEW JENKINS
Bottom/Toe 7/1/2021 Partial Inspection MATTHEW JENKINS
Final 7/1/2021 Partial Inspection MATTHEW JENKINS
Rough 7/1/2021 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 5/18/2022 Partial Inspection AL GAMBLE
Irrigation/Landscape 5/18/2022 Partial Inspection AL GAMBLE
Bottom/Toe 11/17/2022 Approved AL GAMBLE
Final 11/17/2022 Not Ready for Inspection AL GAMBLE
Rough 11/17/2022 Approved AL GAMBLE
Final 12/6/2022 Permit Finaled AL GAMBLE