210 E LINNIE CL 90291
Certificate Information: 210 E LINNIE CL 90291
- Application / Permit
- 18030-10000-05678
- Plan Check / Job No.
- B18LA17304
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE (R & R, 285 CY)
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 12/7/2022
Permit Application Status History
| Submitted | 8/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | DEVIN GORDON |
| Corrections Issued | 9/10/2018 | DEVIN GORDON |
| Quality Review Completed | 9/13/2018 | DAVID CHANG |
| Building Plans Picked Up | 9/20/2018 | APPLICANT |
| Green Plans Picked Up | 9/20/2018 | APPLICANT |
| Plan Check Approved | 2/12/2019 | DEVIN GORDON |
| Issued | 2/4/2020 | LADBS |
| Permit Finaled | 12/6/2022 | AL GAMBLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/8/2018 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Engineer | Nester, Melvin Russell Jr; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Tucker, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/11/2021 | Corrections Issued | MATTHEW JENKINS |
| Initial Grading | 4/20/2021 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 4/22/2021 | Approved | JONATHAN HOM |
| Initial Grading | 4/26/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 4/27/2021 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 5/4/2021 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 5/18/2021 | Partial Approval | JONATHAN HOM |
| Special/Order Compliance | 5/18/2021 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 5/21/2021 | Partial Approval | MATTHEW JENKINS |
| Excavation | 5/25/2021 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 7/1/2021 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 7/1/2021 | Partial Inspection | MATTHEW JENKINS |
| Final | 7/1/2021 | Partial Inspection | MATTHEW JENKINS |
| Rough | 7/1/2021 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 5/18/2022 | Partial Inspection | AL GAMBLE |
| Irrigation/Landscape | 5/18/2022 | Partial Inspection | AL GAMBLE |
| Bottom/Toe | 11/17/2022 | Approved | AL GAMBLE |
| Final | 11/17/2022 | Not Ready for Inspection | AL GAMBLE |
| Rough | 11/17/2022 | Approved | AL GAMBLE |
| Final | 12/6/2022 | Permit Finaled | AL GAMBLE |