2535 W TEMPLE ST 90026

Certificate Information: 2535 W TEMPLE ST 90026

Application / Permit
18030-10000-05611
Plan Check / Job No.
B18LA17098
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
SITE PREP GRADING WORK FOR PARKING LOT AND RETAINING WALL BACKFILL. 475 CU.YDS. GPI 20030-20000-01480: G/S REQUIRED. SHORING
Permit Issued
Issued on 10/26/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/16/2025

Permit Application Status History

Submitted 8/15/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 JESSE JIMENEZ
Corrections Issued 9/10/2018 JESSE JIMENEZ
Quality Review Completed 9/10/2018 DAVID CHANG
Applicant returned to address corrections 9/21/2020 JESSE JIMENEZ
Building Plans Picked Up 9/22/2020 APPLICANT
Applicant returned to address corrections 10/13/2021 JESSE JIMENEZ
Applicant returned to address corrections 10/20/2021 JESSE JIMENEZ
Applicant returned to address corrections 6/22/2023 ARSALAN SHABESTARI
Applicant returned to address corrections 7/18/2023 ARSALAN SHABESTARI
Plan Check Approved 9/14/2023 ARSALAN SHABESTARI
Issued 10/26/2023 APPLICANT
Permit Finaled 1/16/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

Low Impact Development Cleared 2/7/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/17/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/20/2020 RENZ SORIANO
Work Adjacent to Public Way Cleared 8/27/2020 ARMEN SARKISIAN
Grading Pre-Inspection Cleared 9/21/2020 JESSE JIMENEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/22/2024 Partial Inspection JONATHAN HOM
Initial Grading 9/25/2024 Corrections Issued RUSSELL BONVOULOIR
Bottom/Toe 10/7/2024 Partial Approval ALEXANDER HELFER
Bottom/Toe 10/11/2024 Partial Approval RUSSELL BONVOULOIR
Fill/Backfill 10/21/2024 Partial Approval JONATHAN HOM
Sub-Drain 10/25/2024 Corrections Issued RUSSELL BONVOULOIR
Bottom/Toe 11/12/2024 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 11/22/2024 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 12/3/2024 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 1/16/2025 Approved RUSSELL BONVOULOIR
Bottom/Toe 1/16/2025 Approved RUSSELL BONVOULOIR
Final 1/16/2025 Permit Finaled RUSSELL BONVOULOIR
Rough 1/16/2025 Approved RUSSELL BONVOULOIR