- Work Description
- PROPOSED ROUGH GRADING FOR 6 SINGLE FAMILY RESIDENCE. LOT SUBDIVISION PER APPROVED TENT. TR. NO. 61414. CUT=35 C.Y., FILL=1,658 C.Y.; IMPORT 1,623 C.Y. PREVIOUS PLAN CHECK NO. G14LA00184. 14030-10000-06261. 1OF2
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/13/2025
Permit Application Status History
| Submitted | 4/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2018 | DAN RYAN EVANGELISTA |
| Corrections Issued | 5/7/2018 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 5/18/2022 | DAN RYAN EVANGELISTA |
| Issued | 5/18/2022 | APPLICANT |
| Permit Finaled | 2/13/2025 | ROBERT PINA |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 5/7/2018 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 5/15/2018 | AMMAR ELTAWIL |
| Stormwater Pollution Mitigatn | Cleared | 5/15/2018 | AMMAR ELTAWIL |
| Work Adjacent to Public Way | Cleared | 5/15/2018 | BOK GOH |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2018 | LEE GUILBEAUX |
| Permit | Cleared | 6/6/2018 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 6/6/2018 | DAISY BENICIA |
| ZI | Cleared | 6/6/2018 | DAISY BENICIA |
| Roof/Waste drainage to street | Cleared | 8/14/2019 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 5/16/2022 | NOAH MCCOY |
Contact Information
| Contractor | G N L Development Inc; Lic. No.: 981677-B | 5939 TOPEKA DRIVE TARZANA, CA 91356 |
| Engineer | Boghossian, George Gourgen; Lic. No.: C34361 | 1101 KILDONAN DRIVE GLENDALE, CA 91207 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/27/2022 | Approved | KIRK LINKLATER |
| Bottom/Toe | 6/28/2022 | Partial Approval | KIRK LINKLATER |
| Bottom/Toe | 6/30/2022 | Partial Approval | KIRK LINKLATER |
| Bottom/Toe | 7/1/2022 | Approved | KIRK LINKLATER |
| Rough | 6/7/2023 | Approved | ROBERT PINA |
| Approved Compaction Report | 6/15/2023 | Approved | ROBERT PINA |
| Final | 2/13/2025 | Permit Finaled | ROBERT PINA |
| SUSMP-Std. Urban Storm Water | 2/13/2025 | Approved | ROBERT PINA |