1660 N CASALE ROAD 90272

Certificate Information: 1660 N CASALE ROAD 90272

Application / Permit
18030-10000-02717
Plan Check / Job No.
B18LA07800
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING. 5 OF 5. BF 20006 APPROVED FOR AN EXPORT OF 3,400 CUBIC YARDS
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
Permit Finaled on 11/24/2025

Permit Application Status History

Submitted 4/23/2018 APPLICANT
Green Plans Picked Up 5/3/2018 APPLICANT
Assigned to Plan Check Engineer 5/10/2018 JOE VO
Corrections Issued 5/21/2018 JOE VO
Quality Review Completed 5/23/2018 GARO TELMI
Applicant returned to address corrections 3/18/2021 JOE VO
Applicant returned to address corrections 3/22/2021 JOE VO
Plan Check Approved 3/24/2021 JOE VO
Issued 6/15/2021 APPLICANT
Building Plans Picked Up 6/16/2021 APPLICANT
Permit Finaled 11/21/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Haul Route Cleared 3/30/2021 VERONICA LOPEZ

Contact Information

Contractor Aragon Fine Homes Inc; Lic. No.: 992249-B 766 NORTH WORKMAN STREET      SAN FERNANDO, CA 91340

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 7/26/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/2/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/4/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/5/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/12/2021 No Access for Inspection MATTHEW JENKINS
Deputy Grading 8/19/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/20/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/23/2021 Partial Approval MATTHEW JENKINS
Deputy Grading 8/25/2021 No Access for Inspection MATTHEW JENKINS
Sub-Drain 9/13/2022 Partial Approval TIMOTHY POWELL
Bottom/Toe 9/11/2023 Corrections Issued JOHNNY MIRANDA
Bottom/Toe 9/14/2023 Approved JOHNNY MIRANDA
Rough 9/21/2023 Partial Inspection JOHNNY MIRANDA
Rough 7/1/2024 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 9/26/2024 Approved MATTHEW JENKINS
Final 9/30/2024 Not Ready for Inspection VASIL MIHALEV
Rough 9/30/2024 Approved VASIL MIHALEV
Drainage Devices/Catch Basin 11/19/2024 Partial Inspection AL GAMBLE
Final 4/15/2025 Corrections Issued JOHNNY MIRANDA
Irrigation/Landscape 5/6/2025 Partial Inspection LANNY MERRICK
Final 11/21/2025 Permit Finaled JOHNNY MIRANDA