5320 N CARTWRIGHT AVE 1-46 91601
Certificate Information: 5320 N CARTWRIGHT AVE 1-46 91601
- Application / Permit
- 18020-30000-01601
- Plan Check / Job No.
- B18WL03556
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- shoring for new apt building
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/14/2023
Permit Application Status History
| Submitted | 6/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2018 | TARIK SAOUD |
| Corrections Issued | 9/17/2018 | TARIK SAOUD |
| Quality Review Completed | 9/27/2018 | KAMRAN GHOTBI RAVANDI |
| Disabled Access Plans Picked Up | 10/9/2018 | APPLICANT |
| Green Plans Picked Up | 10/9/2018 | APPLICANT |
| Applicant returned to address corrections | 3/30/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 4/21/2022 | TARIK SAOUD |
| Plan Check Approved | 8/29/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Issued | 9/8/2022 | APPLICANT |
| Permit Finaled | 9/14/2023 | ROBERT DAVIS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | CARLOS AGUILERA |
| Work Adjacent to Public Way | Cleared | 8/22/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | P And N Construction Inc; Lic. No.: 800653-B | 8730 WILSHIRE BLVD #202 BEVERLY HILLS, CA 90211 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2022 | Approved | ROBERT DAVIS |
| Deputy Grading | 9/27/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Grading | 9/28/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 9/29/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 9/30/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/3/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Grading | 10/4/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/5/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/6/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/7/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/11/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/12/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/13/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 10/14/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 11/2/2022 | Conditional Approval | ROBERT DAVIS |
| Final | 9/14/2023 | Permit Finaled | ROBERT DAVIS |