4351 N VANALDEN AVE 91356

Certificate Information: 4351 N VANALDEN AVE 91356

Application / Permit
18020-20000-02976
Plan Check / Job No.
B18VN17227
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
Two (N) Retaining Walls per Eng (L1= 138'-8" , H1= 10'-0" ; L2= 190'-11" , H2= 10'-0").
Permit Issued
Issued on 6/8/2020
Issuing Office
Valley
Current Status
Permit Finaled on 8/29/2024

Permit Application Status History

Submitted 10/5/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 OMID HEDAYAT
Green Plans Picked Up 11/6/2018 APPLICANT
Corrections Issued 11/19/2018 OMID HEDAYAT
Quality Review Completed 12/3/2018 STEVEN KIM
Building Plans Picked Up 1/3/2019 APPLICANT
Applicant returned to address corrections 3/23/2020 OMID HEDAYAT
Applicant returned to address corrections 5/4/2020 OMID HEDAYAT
Applicant returned to address corrections 5/26/2020 OMID HEDAYAT
Plan Check Approved 5/26/2020 OMID HEDAYAT
Issued 6/8/2020 LADBS
Permit Finaled 8/29/2024 MANUEL TEJADA

Permit Application Clearance Information

Landscape for retaining wall Cleared 3/12/2020 VINCENT QUITORIANO
Excavation more than 5-ft deep Cleared 3/23/2020 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/28/2020 OMID HEDAYAT

Contact Information

Contractor Owner-Builder       ,
Engineer Berger,, Phillip M; Lic. No.: C13128 6250 CANOGA AVE STE 465      WOODLAND HILLS, CA 91367
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2020 Partial Approval ALEXANDER ANDREWS
Piling/Pier/Caisson 12/11/2020 Partial Approval ALEXANDER ANDREWS
Pre-Inspection 12/11/2020 Approved ALEXANDER ANDREWS
Deputy Grading 12/14/2020 Approved ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 12/17/2020 Approved ALEXANDER ANDREWS
Piling/Pier/Caisson 12/17/2020 Partial Approval ALEXANDER ANDREWS
Pre-Inspection 12/17/2020 Not Ready for Inspection ALEXANDER ANDREWS
Footing/Foundation/Slab 1/20/2021 Partial Approval ALEXANDER ANDREWS
Deputy Reinf. Concrete 1/25/2021 Approved ALEXANDER ANDREWS
Masonry Wall/Backfill 2/25/2021 Partial Approval ALEXANDER ANDREWS
Deputy Shotcrete 2/26/2021 Approved ALEXANDER ANDREWS
Deputy Shotcrete 3/2/2021 Approved ALEXANDER ANDREWS
Deputy Wood Construction 3/31/2021 Conditional Approval DAVID SANDOVAL
Deputy Reinf. Concrete 4/14/2021 Approved ALEXANDER ANDREWS
Piling/Pier/Caisson 4/14/2021 Partial Approval ALEXANDER ANDREWS
Piling/Pier/Caisson 4/16/2021 Partial Approval ALEXANDER ANDREWS
Piling/Pier/Caisson 4/20/2021 Partial Approval ALEXANDER ANDREWS
Footing/Foundation/Slab 5/4/2021 Partial Approval ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 5/17/2021 Partial Approval ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 5/18/2021 Partial Approval ALEXANDER ANDREWS
Deputy Shotcrete 5/21/2021 Approved ALEXANDER ANDREWS
Masonry Wall/Backfill 5/28/2021 Partial Approval ALEXANDER HELFER
Final 5/5/2022 Not Ready for Inspection LANNY MERRICK
Final 8/27/2024 Corrections Issued MANUEL TEJADA
Final 8/29/2024 Permit Finaled MANUEL TEJADA