3699 N ALTA MESA DR 91604

Certificate Information: 3699 N ALTA MESA DR 91604

Application / Permit
18020-10002-03653
Plan Check / Job No.
B24LA34234
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
PERMIT 01: SUPPLEMENTAL PERMIT (REF. 18020-10000-03653) FOR REVISIONS TO SITE RET. WALLS (ADD'L ON-STIE RET. WALLS) PERMIT 02: SUPPLEMENTAL PERMIT (REF. 17030-10000-00654) FOR REVISED GRADING Supplemental Permit to #17030-10000-00654 to revise Grading
Permit Issued
Issued on 12/17/2024
Issuing Office
Current Status
Permit Finaled on 7/1/2025

Permit Application Status History

Submitted 12/3/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 JOE VO
Plan Check Approved 12/16/2024 JOE VO
Issued 12/17/2024 APPLICANT
Permit Finaled 6/30/2025 ALEXANDER HELFER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Western Built Construction Inc; Lic. No.: 951783-B       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/8/2025 Corrections Issued MANUEL TEJADA
Deputy Grading 1/9/2025 Conditional Approval JUAN VALENZUELA
Special/Order Compliance 1/9/2025 Corrections Issued MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 1/10/2025 Partial Inspection MANUEL TEJADA
Piling/Pier/Caisson 1/10/2025 Not Ready for Inspection MANUEL TEJADA
Deputy Reinf. Concrete 1/16/2025 Approved MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 1/16/2025 Partial Approval MANUEL TEJADA
Piling/Pier/Caisson 1/16/2025 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 1/17/2025 Approved MANUEL TEJADA
Deputy Reinf. Concrete 1/23/2025 Approved MANUEL TEJADA
Piling/Pier/Caisson 1/23/2025 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 1/31/2025 Approved MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 1/31/2025 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 2/4/2025 Approved MANUEL TEJADA
Grading Pre-Inspection 2/19/2025 Approved MANUEL TEJADA
Interior/Exterior Lathing 2/19/2025 Approved MANUEL TEJADA
Masonry Wall/Backfill 2/20/2025 Partial Approval CHARLES POWELL
Final 6/30/2025 Permit Finaled ALEXANDER HELFER