832 N MARIPOSA AVE 90029
Certificate Information: 832 N MARIPOSA AVE 90029
- Application / Permit
- 18020-10000-03681
- Plan Check / Job No.
- B18LA26941
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR 2 LEVELS OF SUBTERRANEAN PARKING OF A NEW APARTMENT.
- Permit Issued
- Issued on 12/17/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | QUAN NGHIEM |
| Corrections Issued | 1/22/2019 | QUAN NGHIEM |
| Quality Review Completed | 1/24/2019 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 1/29/2019 | APPLICANT |
| Plan Check Approved | 11/14/2019 | QUAN NGHIEM |
| Issued | 12/17/2019 | LADBS |
| Permit Finaled | 11/10/2022 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Frymer Construction; Lic. No.: 860661-B | 2461 SANTA MONICA BLVD 134 SANTA MONICA, CA 90404 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 1/28/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 1/28/2020 | Approved | DANIEL MC AULIFFE |
| Deputy Grading | 1/29/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/29/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Grading | 1/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Rough | 1/30/2020 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Grading | 1/31/2020 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Steel/Welding | 2/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/18/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/19/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 2/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 2/21/2020 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Steel/Welding | 2/21/2020 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Steel/Welding | 2/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/25/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/26/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Grading | 4/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/21/2020 | Conditional Approval | RAFAEL ESPINOZA |