11329 W CANTON DR 91604

Certificate Information: 11329 W CANTON DR 91604

Application / Permit
18020-10000-03413
Plan Check / Job No.
B18LA24439
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL, Total Length is 50 ft and max. 5ft ht.
Permit Issued
Issued on 6/23/2020
Issuing Office
Current Status
Permit Finaled on 4/9/2021

Permit Application Status History

Submitted 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 TSE MING HUANG
Corrections Issued 12/5/2018 TSE MING HUANG
Quality Review Completed 12/11/2018 FELIX FIGUEROA
Applicant returned to address corrections 12/20/2018 TSE MING HUANG
Applicant returned to address corrections 1/25/2019 TSE MING HUANG
Applicant returned to address corrections 11/15/2019 TSE MING HUANG
Applicant returned to address corrections 12/13/2019 TSE MING HUANG
Applicant returned to address corrections 1/3/2020 TSE MING HUANG
Applicant returned to address corrections 1/28/2020 TSE MING HUANG
Applicant returned to address corrections 5/8/2020 TSE MING HUANG
Applicant returned to address corrections 5/12/2020 TSE MING HUANG
Building Plans Picked Up 6/2/2020 APPLICANT
Plan Check Approved 6/17/2020 TSE MING HUANG
Issued 6/23/2020 APPLICANT
Permit Finaled 4/9/2021 ARAM AVEDISIAN

Permit Application Clearance Information

Specific Plan Cleared 11/16/2018 DOMINICK ORTIZ
Eng Process Fee Ord 176,300 Cleared 11/15/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 11/15/2019 THOMAS LANG
Grading Pre-Inspection Cleared 1/3/2020 TSE MING HUANG

Contact Information

Contractor Ross Construction; Lic. No.: 977430-B 1416 N UKIAH WAY      UPLAND, CA 91786
Engineer Mutka,, Jason Richard; Lic. No.: C72255 PO BOX 77144      CORONA, CA 92877
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2020 Not Ready for Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 8/24/2020 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/10/2020 Conditional Approval ARAM AVEDISIAN
Masonry Wall/Backfill 9/16/2020 Partial Approval ARAM AVEDISIAN
Masonry Wall/Backfill 9/24/2020 Not Ready for Inspection ARAM AVEDISIAN
Final 4/9/2021 Permit Finaled ARAM AVEDISIAN