1100 W TEMPLE ST 90012
Certificate Information: 1100 W TEMPLE ST 90012
- Application / Permit
- 18020-10000-00930
- Plan Check / Job No.
- B18LA06605
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- **EARLY START PERMIT :PROPOSED 282'-0" LONG WITH MAX. 15'-0" HEIGHT TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR NEW 8 STORY, 54 UNITS APARTMENT BUILDING . (5 STORIES OF TYPE III-A APRATMENT OVER 3 STORIES TYPE I-A PARKING GARAGE ( TOTAL 8 STORIES) . .
- Permit Issued
- Issued on 6/17/2019
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 7/17/2020
- Certificate of Occupancy
- CofO Corrected More Information
Permit Application Status History
| Submitted | 4/5/2018 | APPLICANT |
| Green Plans Picked Up | 4/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | GARO TELMI |
| Corrections Issued | 5/14/2018 | GARO TELMI |
| Quality Review Completed | 5/18/2018 | JOHN FRANCIA |
| Building Plans Picked Up | 5/24/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 7/25/2018 | APPLICANT |
| Applicant returned to address corrections | 8/29/2018 | GARO TELMI |
| Applicant returned to address corrections | 9/19/2018 | GARO TELMI |
| Applicant returned to address corrections | 10/1/2018 | GARO TELMI |
| Applicant returned to address corrections | 10/23/2018 | GARO TELMI |
| Applicant returned to address corrections | 11/7/2018 | GARO TELMI |
| Applicant returned to address corrections | 1/9/2019 | GARO TELMI |
| Applicant returned to address corrections | 4/15/2019 | GARO TELMI |
| Applicant returned to address corrections | 5/1/2019 | GARO TELMI |
| Plan Check Approved | 6/3/2019 | GARO TELMI |
| Issued | 6/17/2019 | LADBS |
| Permit Finaled | 7/17/2020 | JAMES POWERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2018 | CELINA MORENO |
| Address approval | Cleared | 9/7/2018 | CELINA MORENO |
| Highway dedication | Cleared | 9/7/2018 | CELINA MORENO |
| Permit | Cleared | 9/7/2018 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/7/2018 | CELINA MORENO |
| Sewer availability | Cleared | 9/7/2018 | CELINA MORENO |
| Green Code | Cleared | 9/12/2018 | GARO TELMI |
| DAS Clearance | Cleared | 9/13/2018 | GARO TELMI |
| Abandoned oil well | Cleared | 9/21/2018 | GEORGE SUCHAND |
| Hydrant and Access approval | Cleared | 9/21/2018 | GEORGE SUCHAND |
| Bicycle Parking | Cleared | 10/26/2018 | KARAN PATEL |
| Encroachment in public way | Cleared | 10/26/2018 | KARAN PATEL |
| Low Impact Development | Cleared | 1/23/2019 | RYAN HUDSON |
| Stormwater Pollution Mitigatn | Cleared | 1/23/2019 | RYAN HUDSON |
| Excavation more than 5-ft deep | Cleared | 3/29/2019 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 5/6/2019 | BOK GOH |
| Driveway location | Cleared | 5/7/2019 | MOHAMMAD HASAN |
| Fire Marshall Fire Life Safety | Cleared | 5/7/2019 | MENOA AGHAJANI |
| Internal circulation | Cleared | 5/7/2019 | MOHAMMAD HASAN |
| Miscellaneous | Cleared | 5/7/2019 | DIANA JIMENEZ |
| Miscellaneous | Cleared | 5/7/2019 | DIANA JIMENEZ |
| Opn space landscape/Water mgmt | Cleared | 5/7/2019 | DIANA JIMENEZ |
| Specific Plan | Cleared | 5/7/2019 | MOHAMMAD HASAN |
| ZA Case | Cleared | 5/7/2019 | DIANA JIMENEZ |
| DCP conditions approval | Cleared | 5/13/2019 | JAMES MCCARTHY |
| Density Bonus 12.22.A.25 | Cleared | 5/13/2019 | JAMES MCCARTHY |
| Miscellaneous | Cleared | 5/15/2019 | DIANA JIMENEZ |
| Site Plan review | Cleared | 5/15/2019 | DIANA JIMENEZ |
| Specific Plan | Cleared | 5/15/2019 | DIANA JIMENEZ |
Contact Information
| Contractor | Forza Construction Inc; Lic. No.: 914162-B | 25243 AVENUE TIBBITS VALENCIA, CA 91355 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Fitzgerald-Kennedy,, Mary Jane; Lic. No.: L6263 | 10980 E VALLEY VIEW DRIVE GOLD CANYON, AZ 85118 |
| Engineer | Hattar,, Basil Ibrahim; Lic. No.: GE2734 | 3525 PARK MEADOW CT PALMDALE, CA 93551 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2019 | Partial Approval | LESLIE TRUJILLO |
| Pre-Inspection | 8/8/2019 | Corrections Issued | LESLIE TRUJILLO |
| Deputy Grading | 8/19/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 8/20/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 8/21/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 8/26/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 8/27/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 9/4/2019 | Conditional Approval | LESLIE TRUJILLO |
| Final | 11/18/2019 | Not Ready for Inspection | LESLIE TRUJILLO |
| SWPPP-Const. Storm Water | 11/26/2019 | Completed | DANIEL COLLINS |