1371 N TOWER GROVE DR 90210

Certificate Information: 1371 N TOWER GROVE DR 90210

Application / Permit
18020-10000-00554
Plan Check / Job No.
B18LA04035
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ELEVATED SWIMMING POOL ON PILES MULTIPLE 2 OF 4
Permit Issued
Issued on 11/13/2018
Issuing Office
Metro
Current Status
Issued on 11/13/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/2/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 AUNG SOE
Corrections Issued 4/2/2018 AUNG SOE
Quality Review Completed 4/11/2018 ARMEN JIVALAGIAN
Building Plans Picked Up 4/16/2018 APPLICANT
Plan Check Approved 11/13/2018 AUNG SOE
Issued 11/13/2018 LADBS

Permit Application Clearance Information

CPC Cleared 6/28/2018 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 7/9/2018 CELINA MORENO
Low Impact Development Cleared 7/9/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 7/9/2018 CELINA MORENO
Sewer availability Cleared 11/13/2018 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201
Engineer Markov, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 12/5/2018 Conditional Approval CARLOS MATAMOROS
Deputy Grading 12/6/2018 Partial Approval MATT KELLERMAN
Deputy Grading 12/7/2018 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 1/3/2019 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 1/3/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/9/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/7/2019 Partial Approval CARLOS MATAMOROS
Pre-Gunite 3/13/2025 Corrections Issued SEAN HAUPT
Pre-Gunite 3/28/2025 Not Ready for Inspection SEAN HAUPT
Pre-Gunite 4/2/2025 Corrections Issued SEAN HAUPT
Pre-Gunite 4/4/2025 Approved SEAN HAUPT
Deputy Steel/Welding 5/6/2025 Conditional Approval MICHAEL PELHAM
Gunite 8/4/2025 Not Ready for Inspection SEAN HAUPT