2622 W SOUTHWEST DR 90043

Certificate Information: 2622 W SOUTHWEST DR 90043

Application / Permit
18016-70000-38363
Plan Check / Job No.
B18SL01738
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE GARAGE INTO AN ADU PER AB494 AND SB229. COMPLY WITH DEPT. ORDER EFECTIVE DATE 6/20/2017. PERMIT WILL EXPIRE 30 DAYS FROM DATE OF ISSUANCE. REMOVE THE UNPERMITTED CONSTRUCTION AT EAST SIDE OF PROPOSED ADU.
Permit Issued
Issued on 3/19/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 8/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 WESLEY FARRELL
Corrections Issued 11/29/2018 WESLEY FARRELL
Applicant returned to address corrections 1/23/2019 WESLEY FARRELL
Plan Check Approved 2/7/2019 WESLEY FARRELL
Issued 3/19/2019 LADBS
CofO in Progress 8/21/2020 KIM BEAUCHAMP
Permit Finaled 8/31/2020 BRUCE TODD
CofO Issued 8/31/2020 BRUCE TODD
Permit Finaled 8/31/2020 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 12/13/2018 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 12/13/2018 KARAN PATEL
Sewer availability Cleared 12/13/2018 KARAN PATEL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/17/2019 Approved JAMES VORHIS
Footing/Foundation/Slab 8/22/2019 Corrections Issued JAMES VORHIS
Pre-Inspection 8/22/2019 Approved JAMES VORHIS
Footing/Foundation/Slab 9/16/2019 Corrections Issued JAMES VORHIS
Footing/Foundation/Slab 10/3/2019 Approved JAMES VORHIS
Footing/Foundation/Slab 11/21/2019 Approved KIM BEAUCHAMP
Wood Frame 2/28/2020 Corrections Issued KIM BEAUCHAMP
PLUMBING-Rough 3/26/2020 Corrections Issued DANIEL GONZALEZ
Wood Frame 3/26/2020 Corrections Issued DANIEL GONZALEZ
Footing/Foundation/Slab 4/1/2020 Approved DANIEL GONZALEZ
PLUMBING-Rough 4/1/2020 Approved DANIEL GONZALEZ
Wood Frame 4/9/2020 Not Ready for Inspection KIM BEAUCHAMP
BUILDING-Rough-Frame 4/27/2020 Approved DANIEL GONZALEZ
ELECTRICAL-Rough 4/27/2020 Approved DANIEL GONZALEZ
HVAC-Rough 4/27/2020 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 4/27/2020 Partial Approval DANIEL GONZALEZ
Insulation 5/1/2020 Approved KIM BEAUCHAMP
Drywall Nailing 5/15/2020 Approved KIM BEAUCHAMP
Service/Power Release 7/23/2020 Approved KIM BEAUCHAMP
SGSOV-Seismic Gas S/O Valve 7/31/2020 SGSOV Not Ready ENRIQUE PREZA
Final 8/6/2020 Corrections Issued KIM BEAUCHAMP
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Approved KIM BEAUCHAMP
Smoke Detectors 8/6/2020 Corrections Issued KIM BEAUCHAMP
Final 8/7/2020 Conditional Approval KIM BEAUCHAMP
Final 8/21/2020 OK to Issue CofO KIM BEAUCHAMP
Smoke Detectors 8/21/2020 Approved KIM BEAUCHAMP