2940 S VICTORIA AVE 90016
Certificate Information: 2940 S VICTORIA AVE 90016
- Application / Permit
- 18016-70000-15941
- Plan Check / Job No.
- B18SL00744
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 8/16/2018
- Issuing Office
- South Los Angeles
- Current Status
- CofO Corrected on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2018 | JOSHUA DIAZ |
| Corrections Issued | 5/18/2018 | JOSHUA DIAZ |
| Applicant returned to address corrections | 6/14/2018 | LUKE GONZALES |
| Plan Check Approved | 8/14/2018 | JOSHUA DIAZ |
| Issued | 8/16/2018 | LADBS |
| CofO in Progress | 2/28/2019 | RONALD MYRICK |
| CofO Issued-Status Void | 2/28/2019 | RONALD MYRICK |
| Permit Finaled-Status Void | 2/28/2019 | RONALD MYRICK |
| Re-Activate Permit | 9/5/2023 | DEROLD HAUFF |
| CofO Corrected | 9/6/2023 | DEROLD HAUFF |
| Permit Finaled | 9/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2018 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2018 | KAREN LE |
| Roof/Waste drainage to street | Cleared | 6/5/2018 | KAREN LE |
| Sewer availability | Cleared | 6/5/2018 | KAREN LE |
| Construction near power lines | Cleared | 8/6/2018 | RIDWAN HARDY |
Contact Information
| Contractor | Golden Point Construction; Lic. No.: 965193-B | 731 EAST 75TH STREET LOS ANGELES, CA 90001 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/6/2018 | Approved | LUIS ALVAREZ |
| Rough-Elec/Plmb/HVAC | 9/6/2018 | Approved | LUIS ALVAREZ |
| Interior/Exterior Lathing | 9/7/2018 | Not Ready for Inspection | LUIS ALVAREZ |
| Interior/Exterior Lathing | 9/12/2018 | Partial Approval | LUIS ALVAREZ |
| Insulation | 9/19/2018 | Partial Approval | LUIS ALVAREZ |
| Interior/Exterior Lathing | 9/19/2018 | Approved | LUIS ALVAREZ |
| BUILDING-Rough-Frame | 9/24/2018 | Approved | LUIS ALVAREZ |
| Drywall Nailing | 9/28/2018 | Not Ready for Inspection | LUIS ALVAREZ |
| Drywall Nailing | 10/3/2018 | Approved | LUIS ALVAREZ |
| Final | 12/11/2018 | Corrections Issued | LUIS ALVAREZ |
| SGSOV-Seismic Gas S/O Valve | 12/11/2018 | SGSOV Approved | LUIS ALVAREZ |
| Smoke Detectors | 12/11/2018 | Approved | LUIS ALVAREZ |
| Final | 1/17/2019 | Not Ready for Inspection | LUIS ALVAREZ |
| Final | 2/11/2019 | Corrections Issued | LUIS ALVAREZ |
| Final | 2/28/2019 | OK to Issue CofO | RONALD MYRICK |