622 E 75TH ST 90001

Certificate Information: 622 E 75TH ST 90001

Application / Permit
18016-70000-10117
Plan Check / Job No.
B18SL00490
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 4/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2018 APPLICANT
Assigned to Plan Check Engineer 6/26/2018 JOSHUA DIAZ
Corrections Issued 6/26/2018 JOSHUA DIAZ
Plan Check Approved 7/9/2018 LUKE GONZALES
Plan Check Approved 7/9/2018 LUKE GONZALES
Issued 4/9/2020 LADBS
Building Plans Picked Up 4/10/2020 APPLICANT
CofO in Progress 6/20/2023 MICHAEL LEWIS
Permit Finaled 6/29/2023 DEROLD HAUFF
CofO Issued 6/29/2023 DEROLD HAUFF
Permit Finaled 6/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 6/15/2018 RIDWAN HARDY
Address approval Cleared 7/5/2018 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 7/5/2018 JOSEPH RHYU
Sewer availability Cleared 7/5/2018 JOSEPH RHYU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 12/20/2021 Not Ready for Inspection ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Not Ready for Inspection ADAM ESCOTO
ELECTRICAL-Rough 1/25/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 1/25/2022 Approved LILIANA PORTILLO
Insulation 1/25/2022 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 1/25/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 1/27/2022 Partial Approval LILIANA PORTILLO
Underground Mechanical 1/27/2022 Partial Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 2/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/17/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/17/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/17/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 3/9/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 3/9/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 3/14/2022 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/14/2022 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/16/2022 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 3/17/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 3/17/2022 Approved LILIANA PORTILLO
HVAC-Rough 3/17/2022 Approved LILIANA PORTILLO
Insulation 3/17/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 3/30/2022 Approved LILIANA PORTILLO
Drywall Nailing 3/30/2022 Approved LILIANA PORTILLO
Insulation 3/30/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/30/2022 Approved LILIANA PORTILLO
Final 2/24/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 2/24/2023 Approved LILIANA PORTILLO
Final 3/13/2023 No Access for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 3/24/2023 Corrections Issued LILIANA PORTILLO
Final 3/24/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/24/2023 Conditional Approval LILIANA PORTILLO
PLUMBING-Final 3/24/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved LILIANA PORTILLO
Final 5/1/2023 Partial Inspection MICHAEL LEWIS
Final 6/16/2023 OK to Issue CofO MICHAEL LEWIS