3358 N OAK GLEN DR 90068

Certificate Information: 3358 N OAK GLEN DR 90068

Application / Permit
18016-40000-29265
Plan Check / Job No.
B18SP00932
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing storage area, at lower leve, to a bedroom and bathroom.
Permit Issued
Issued on 3/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 MANUEL GARCIA
Corrections Issued 9/24/2018 MANUEL GARCIA
Quality Review Completed 10/1/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 10/11/2018 APPLICANT
Green Plans Picked Up 1/22/2019 APPLICANT
Plan Check Approved 2/22/2019 MANUEL GARCIA
Issued 3/7/2019 LADBS
CofO in Progress 3/8/2021 BRAD BESCOS
Permit Finaled 4/13/2021 DEROLD HAUFF
CofO Issued 4/13/2021 DEROLD HAUFF
Permit Finaled 4/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/24/2018 PATRICK MISCHLICH
Sewer availability Cleared 10/24/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/8/2019 ERIK BEASLEY
Green Code Cleared 2/7/2019 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Avila,, Albert Guerrero; Lic. No.: C41726 10034 GLADE AVNENUE      CHATSWORTH, CA 91311

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/23/2019 Corrections Issued BRIAN SULLIVAN
Deputy Drilled-In Anchors 5/1/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 6/10/2019 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/1/2019 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/21/2019 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/21/2019 Not Ready for Inspection BRIAN SULLIVAN
MERV13>=Rough 8/21/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 8/21/2019 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 10/18/2019 Approved RICHARD STEINBACH
PLUMBING-Rough 10/18/2019 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 10/29/2019 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 12/6/2019 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/6/2019 Approved BRIAN SULLIVAN
HVAC-Rough 12/6/2019 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 12/12/2019 Approved BRIAN SULLIVAN
Drywall Nailing 1/10/2020 Approved BRIAN SULLIVAN
Deputy Drilled-In Anchors 1/28/2020 Conditional Approval BRIAN SULLIVAN
Final 5/22/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 5/22/2020 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/22/2020 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 5/22/2020 Approved BRIAN SULLIVAN
Final 6/4/2020 Conditional Approval BRIAN SULLIVAN
MERV13>=Final 6/4/2020 Approved BRIAN SULLIVAN