1805 E 106TH ST 90002
Certificate Information: 1805 E 106TH ST 90002
- Application / Permit
- 18016-40000-21894
- Plan Check / Job No.
- B18SP00698
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) Garage to ADU per WFPP, AB 494, and SB 229
- Permit Issued
- Issued on 11/28/2018
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 7/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2018 | JASON JANGADA |
| Corrections Issued | 8/22/2018 | JASON JANGADA |
| Quality Review Completed | 8/23/2018 | MARJAN SHENASI |
| Building Plans Picked Up | 9/18/2018 | APPLICANT |
| Applicant returned to address corrections | 11/15/2018 | JASON JANGADA |
| Applicant returned to address corrections | 11/27/2018 | JASON JANGADA |
| Applicant returned to address corrections | 11/28/2018 | JASON JANGADA |
| Plan Check Approved | 11/28/2018 | JASON JANGADA |
| Issued | 11/28/2018 | LADBS |
| CofO in Progress | 4/23/2020 | BRIAN CHRISTIAN |
| Permit Finaled | 7/10/2021 | DEROLD HAUFF |
| CofO Issued | 7/10/2021 | DEROLD HAUFF |
| Permit Finaled | 7/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2018 | PHILLIP WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2018 | PHILLIP WILSON |
| Sewer availability | Cleared | 10/18/2018 | PHILLIP WILSON |
Contact Information
| No Data Available. |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2019 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 1/29/2019 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 2/1/2019 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 2/1/2019 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/28/2019 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 3/28/2019 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 4/29/2019 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 4/29/2019 | Approved | DAVID FEILER |
| PLUMBING-Rough | 4/29/2019 | Approved | DAVID FEILER |
| HVAC-Rough | 6/4/2019 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/4/2019 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/11/2019 | Partial Approval | DAVID FEILER |
| Insulation | 6/24/2019 | No Access for Inspection | WILLIAM ROSE |
| Insulation | 6/28/2019 | Corrections Issued | WILLIAM ROSE |
| Insulation | 7/5/2019 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 7/25/2019 | Not Ready for Inspection | WILLIAM ROSE |
| ELECTRICAL-Rough | 7/25/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Insulation | 7/25/2019 | Corrections Issued | WILLIAM ROSE |
| Drywall Nailing | 9/27/2019 | Corrections Issued | WILLIAM ROSE |
| Drywall Nailing | 3/3/2020 | Conditional Approval | WILLIAM ROSE |
| BUILDING-Rough-Frame | 3/13/2020 | Approved | WILLIAM ROSE |
| Final | 3/13/2020 | Corrections Issued | WILLIAM ROSE |
| SGSOV-Seismic Gas S/O Valve | 3/13/2020 | SGSOV Not Ready | WILLIAM ROSE |
| Smoke Detectors | 3/13/2020 | Not Ready for Inspection | WILLIAM ROSE |
| Final | 4/3/2020 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/3/2020 | Approved | EUGENE CASSIDY |
| Final | 4/10/2020 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/10/2020 | SGSOV Approved | EUGENE CASSIDY |
| Final | 4/20/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/23/2020 | Approved | BRIAN CHRISTIAN |
| Final | 4/23/2020 | OK to Issue CofO | BRIAN CHRISTIAN |
| Green Building Final | 4/23/2020 | Approved | BRIAN CHRISTIAN |
| HVAC-Final | 4/23/2020 | Approved | BRIAN CHRISTIAN |
| PLUMBING-Final | 4/23/2020 | Approved | BRIAN CHRISTIAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Approved | BRIAN CHRISTIAN |