10425-10425 1/2 W SUNSET BLVD 90077

Certificate Information: 10425-10425 1/2 W SUNSET BLVD 90077

Application / Permit
18016-30006-15413
Plan Check / Job No.
B19WL02236
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO #18016-30000-15413 TO ADD NEW ATTACHED ACCESSORY DWELLING UNIT PER SB-229 & AB-494 AND MECHANICAL ROOM AREA AT GROUND FLOOR. ADDITION TO (E) DWELLING AND (N) ATTACHED DECK AT 2ND LEVEL. BUILDING IS NOW 3-STORY. INCREASE $300,000.00 PROJECT VALUATION PER INPECTOR - TOTAL VALUATION OF $615,000.00.
Permit Issued
Issued on 3/12/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2019 APPLICANT
Green Plans Picked Up 5/7/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 ERWIN PASCUA
Corrections Issued 5/13/2019 ERWIN PASCUA
Quality Review Completed 5/24/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/28/2019 APPLICANT
Applicant returned to address corrections 7/8/2019 ERWIN PASCUA
Applicant returned to address corrections 1/29/2020 ERWIN PASCUA
Applicant returned to address corrections 2/12/2020 ERWIN PASCUA
Applicant returned to address corrections 3/3/2020 ERWIN PASCUA
Plan Check Approved 3/10/2020 ERWIN PASCUA
Issued 3/12/2020 LADBS
Permit Finaled 10/20/2023 CHRISTOPHER WILSON

Permit Application Clearance Information

Address approval Cleared 2/12/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 2/12/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 2/12/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 2/12/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/12/2020 THOMAS LANG
Sewer availability Cleared 2/12/2020 THOMAS LANG
Hydrant and Access approval Cleared 2/18/2020 ROBERT DUFF
CPC Cleared 3/3/2020 LOUIS ORTEGA
GPI Written Notices Cleared 3/3/2020 ERWIN PASCUA
Grading Pre-Inspection Cleared 3/3/2020 ERWIN PASCUA
Green Code Cleared 3/3/2020 RICHARD GARCIA
Miscellaneous Cleared 3/3/2020 LOUIS ORTEGA
Site Plan review Cleared 3/3/2020 MARITZA PRZEKOP
ZA Case Cleared 3/3/2020 MARITZA PRZEKOP
ZI Cleared 3/3/2020 LOUIS ORTEGA
Low Impact Development Cleared 3/5/2020 MARTIN FRAGOSO
Flood clearance Cleared 3/9/2020 TRACY TATE
Roof/Waste drainage to street Cleared 3/9/2020 JEANIE LAM

Contact Information

Architect Larkin,, Dean A; Lic. No.: C28277 7494 SANTA MONICA BLVD STE 303      WEST HOLLYWOOD, CA 90046
Contractor Builder'S Team Inc; Lic. No.: 636904-B 2259 HONOLULU AVENUE      MONTROSE, CA 91020
Engineer Liston,, Leonard Irvin; Lic. No.: C31902 889 PIERCE CT STE 101      THOUSAND OAKS, CA 91360
Engineer Yenjai, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 5/4/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/4/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/27/2020 Conditional Approval CHRISTOPHER WILSON
FLOOD-Elevation Certificate 5/28/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/28/2020 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/10/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/10/2020 Conditional Approval CHRISTOPHER WILSON
FLOOD-Proofing Certificate 7/10/2020 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 7/10/2020 Corrections Issued CHRISTOPHER WILSON
Wood Frame 7/15/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 9/2/2020 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 9/2/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/3/2020 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 9/3/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/8/2020 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 10/8/2020 Partial Approval ANTHONY MCDOWALL
Reinforced Concrete Frame 10/26/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/30/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/10/2020 Conditional Approval CHRISTOPHER WILSON
FLOOD-Elevation Certificate 12/11/2020 Not Ready for Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 12/11/2020 Partial Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 12/22/2020 Partial Approval MATT KELLERMAN
Piling/Pier/Caisson 12/22/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 1/20/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/21/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/26/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/2/2021 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/13/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 9/13/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 9/20/2021 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 9/20/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 9/20/2021 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/6/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 10/6/2021 Approved CHRISTOPHER WILSON
FLOOD-Proofing Certificate 10/6/2021 Approved CHRISTOPHER WILSON
Green Building Rough 10/6/2021 Approved CHRISTOPHER WILSON
HVAC-Rough 10/6/2021 Approved CHRISTOPHER WILSON
PLUMBING-Rough 10/6/2021 Approved CHRISTOPHER WILSON
Wood Frame 10/6/2021 Approved CHRISTOPHER WILSON
Insulation 10/15/2021 Approved JUAN VALENZUELA
Drywall Nailing 10/26/2021 Approved CHRISTOPHER WILSON
Sewer 6/22/2022 Partial Approval CHRISTOPHER WILSON
Sewer 9/8/2022 Corrections Issued STEPHANIE SWANSON
Gas Test 5/11/2023 Partial Approval BRENDAN LOONEY
Special/Order Compliance 5/11/2023 Corrections Issued BRENDAN LOONEY
Final 6/16/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 6/16/2023 Approved CHRISTOPHER WILSON
Smoke Detectors 6/16/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 6/29/2023 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Elevation Certificate 10/16/2023 Corrections Issued CHRISTOPHER WILSON
Final 10/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/16/2023 Not Ready for Inspection CHRISTOPHER WILSON