10425 W SUNSET BLVD 90077

Certificate Information: 10425 W SUNSET BLVD 90077

Application / Permit
18016-30003-15413
Plan Check / Job No.
B18WL06501
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO #18016-30000-15413 DUE TO 2ND FLOOR ADDITION OVER (E) HIGH CEILING ROOM. VALUATION OF $250,001 UNDER SUPPLEMENTAL PERMIT #18016-30004-15413.
Permit Issued
Issued on 1/7/2019
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2018 APPLICANT
Assigned to Plan Check Engineer 10/25/2018 ERWIN PASCUA
Green Plans Picked Up 10/29/2018 APPLICANT
Corrections Issued 11/2/2018 ERWIN PASCUA
Quality Review Completed 11/9/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/27/2018 APPLICANT
Plan Check Approved 1/7/2019 ERWIN PASCUA
Plan Check Approved 1/7/2019 ERWIN PASCUA
Issued 1/7/2019 LADBS
Permit Finaled 2/14/2024 CHRISTOPHER WILSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/27/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 11/27/2018 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 11/27/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 12/13/2018 STEVE MELGAR
Sewer availability Cleared 12/13/2018 STEVE MELGAR
Green Code Cleared 12/19/2018 DONALD CRICHLOW

Contact Information

Contractor Builder'S Team Inc; Lic. No.: 636904-B 2259 HONOLULU AVENUE      MONTROSE, CA 91020
Engineer Yenjai, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Proofing Certificate 7/31/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 7/31/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/31/2020 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 9/11/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 9/11/2020 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 9/11/2020 Partial Approval CHRISTOPHER WILSON
Final 6/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 6/16/2023 Approved CHRISTOPHER WILSON
Green Building Rough 6/16/2023 Approved CHRISTOPHER WILSON
Wood Frame 6/16/2023 Not Ready for Inspection CHRISTOPHER WILSON