10425 W SUNSET BLVD 90077
Certificate Information: 10425 W SUNSET BLVD 90077
- Application / Permit
- 18016-30000-39738
- Plan Check / Job No.
- B18WL07788
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Servant's Quarters
- Work Description
- COVERED PATIO ADDITION, INTERIOR & EXTERIOR MAJOR REMODEL OF (E) RECREATION ROOM AND SERVANTS' QUARTERS. REMOVE UNPERMITTED ADDITIONS TO RESTORE TO ORIGINAL BUILDING FOOTPRINT.
- Permit Issued
- Issued on 7/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | ERWIN PASCUA |
| Corrections Issued | 12/29/2018 | ERWIN PASCUA |
| Quality Review Completed | 1/8/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 1/14/2019 | APPLICANT |
| Applicant returned to address corrections | 5/7/2019 | ERWIN PASCUA |
| Plan Check Approved | 7/18/2019 | ERWIN PASCUA |
| Plan Check Approved | 7/18/2019 | ERWIN PASCUA |
| Issued | 7/18/2019 | LADBS |
| CofO in Progress | 2/22/2025 | CHRISTOPHER WILSON |
| CofO Issued | 3/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/2/2019 | BARTON HOLMES |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2019 | TAO YANG |
| Flood clearance | Cleared | 5/7/2019 | TAO YANG |
| CPC | Cleared | 7/17/2019 | TREVOR MARTIN |
| Roof/Waste drainage to street | Cleared | 7/17/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 7/17/2019 | TREVOR MARTIN |
Contact Information
| Contractor | Builder'S Team Inc; Lic. No.: 636904-B | 2259 HONOLULU AVENUE MONTROSE, CA 91020 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/30/2019 | Partial Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 9/24/2019 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/30/2019 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 10/10/2019 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 11/4/2019 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/18/2019 | Partial Approval | ANTHONY MCDOWALL |
| FLOOD-Elevation Certificate | 11/26/2019 | Approved | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 11/26/2019 | Partial Approval | ANTHONY MCDOWALL |
| Wood Frame | 1/30/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Partial Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 2/28/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 8/4/2020 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/4/2020 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 8/6/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/6/2020 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 8/11/2020 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/31/2020 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/4/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 9/8/2020 | Corrections Issued | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 9/8/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 9/8/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 11/17/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 12/3/2020 | Corrections Issued | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 12/3/2020 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/3/2020 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/4/2020 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/4/2020 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 12/4/2020 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 12/4/2020 | Approved | CHRISTOPHER WILSON |
| Insulation | 12/8/2020 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 12/11/2020 | Partial Approval | ANTHONY MCDOWALL |
| Drywall Nailing | 1/25/2021 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 2/1/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 2/9/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/16/2021 | Partial Approval | CHRISTOPHER WILSON |
| Sewer | 6/22/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/26/2023 | Partial Approval | CHRISTOPHER WILSON |
| Service/Power Release | 5/26/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 6/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/12/2023 | Approved | CHRISTOPHER WILSON |
| Gas Test | 6/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/30/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 7/10/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 7/18/2023 | Approved | CHRISTOPHER WILSON |
| Final | 2/6/2025 | OK to Issue CofO | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/6/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 2/6/2025 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 2/6/2025 | Approved | CHRISTOPHER WILSON |