332 1/2 N IRVING BLVD 90004

Certificate Information: 332 1/2 N IRVING BLVD 90004

Application / Permit
18016-30000-37229
Plan Check / Job No.
B18WL07333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) garage to Accessory Dwelling Unit. Per AB 494 SB 229.
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 ALFREDO JARA
Corrections Issued 11/21/2018 ALFREDO JARA
Plan Check Approved 12/4/2018 ALFREDO JARA
Issued 7/16/2020 APPLICANT
Building Plans Picked Up 7/22/2020 APPLICANT
CofO in Progress 11/18/2020 CHRIS CHRISTENSEN
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 11/30/2018 JEANETTE VONG
Sewer availability Cleared 11/30/2018 JEANETTE VONG

Contact Information

Contractor Tis, Inc.; Lic. No.: 865091-B 29320 LAS TERRENO LANE      VALENCIA, CA 91354
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/12/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/12/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/26/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/26/2020 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/8/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 9/14/2020 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 9/14/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 9/14/2020 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 9/14/2020 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/22/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 9/22/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 9/22/2020 Partial Approval JOSEPH MCGARRY
Wood Frame 9/22/2020 Partial Approval JOSEPH MCGARRY
Insulation 10/6/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/6/2020 Conditional Approval CHRIS CHRISTENSEN
Shower Pan 10/6/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/16/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 10/16/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/17/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/17/2020 Approved CHRIS CHRISTENSEN
Final 11/17/2020 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/17/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 11/17/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/17/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/17/2020 Approved CHRIS CHRISTENSEN