15931 W ASILOMAR BLVD 90272

Certificate Information: 15931 W ASILOMAR BLVD 90272

Application / Permit
18016-30000-36166
Plan Check / Job No.
B18WL07131
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) storage into an Accessory dwelling unit per AB494 and SB229. Per engineering design.
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 KAVIAN REFAHI
Corrections Issued 11/15/2018 KAVIAN REFAHI
Plan Check Approved 2/25/2020 ALFREDO JARA
Issued 9/2/2020 APPLICANT
Building Plans Picked Up 9/11/2020 APPLICANT
CofO in Progress 5/9/2022 ANDREW NAVE
Permit Finaled 5/16/2022 DANIEL ORRANTE
CofO Issued 5/16/2022 DANIEL ORRANTE
Permit Finaled 5/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Coastal Zone Cleared 2/4/2020 DENZEL HENDERSON
Coastal Zone Cleared 2/4/2020 DENZEL HENDERSON
Coastal Zone Cleared 2/4/2020 DENZEL HENDERSON
Address approval Cleared 2/12/2020 ANTHONY MAINEZ
Sewer availability Cleared 2/12/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/25/2020 DENNIS BRAGIN
Grading Pre-Inspection Cleared 2/25/2020 KAVIAN REFAHI

Contact Information

Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/29/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 11/12/2020 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 11/17/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 11/20/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 12/23/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/23/2020 Approved EVAN COOPER
HVAC-Rough 12/23/2020 Approved EVAN COOPER
PLUMBING-Rough 12/23/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 1/11/2021 Approved ANDREW NAVE
Insulation 1/11/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 1/11/2021 Not Ready for Inspection ANDREW NAVE
Shower Pan 1/11/2021 Approved ANDREW NAVE
Drywall Nailing 1/19/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 1/19/2021 Approved ANDREW NAVE
ELECTRICAL-Final 4/19/2021 Corrections Issued ANDREW NAVE
Final 4/19/2021 Corrections Issued ANDREW NAVE
HVAC-Final 4/19/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 4/19/2021 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 4/19/2021 Approved ANDREW NAVE
ELECTRICAL-Final 4/23/2021 Approved ANDREW NAVE
Final 4/23/2021 Conditional Approval ANDREW NAVE
HVAC-Final 4/23/2021 Approved ANDREW NAVE
PLUMBING-Final 4/23/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved ANDREW NAVE
Final 5/9/2022 OK to Issue CofO ANDREW NAVE