11600 W PICO BLVD 90064
Certificate Information: 11600 W PICO BLVD 90064
- Application / Permit
- 18016-30000-31920
- Plan Check / Job No.
- B18WL06337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- Change of use and tenant improvement from office and retail to medical office and office.
- Permit Issued
- Issued on 2/7/2019
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 10/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | RICARDO RAMIREZ |
| Corrections Issued | 10/15/2018 | RICARDO RAMIREZ |
| Quality Review Completed | 10/25/2018 | TARIK SAOUD |
| Building Plans Picked Up | 10/26/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 10/26/2018 | APPLICANT |
| Green Plans Picked Up | 10/26/2018 | APPLICANT |
| Applicant returned to address corrections | 12/26/2018 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/22/2019 | RICARDO RAMIREZ |
| Plan Check Approved | 1/31/2019 | RICARDO RAMIREZ |
| Issued | 2/7/2019 | LADBS |
| CofO in Progress | 1/22/2020 | JASON BORUTA |
| CofO Issued-Status Void | 2/10/2020 | HENRY BAGHDASSARIAN |
| Permit Finaled-Status Void | 2/10/2020 | HENRY BAGHDASSARIAN |
| Re-Activate Permit | 2/13/2020 | HENRY BAGHDASSARIAN |
| CofO in Progress | 10/28/2020 | HENRY BAGHDASSARIAN |
| CofO in Progress | 10/28/2020 | HENRY BAGHDASSARIAN |
| Permit Finaled | 10/28/2020 | HENRY BAGHDASSARIAN |
| CofO Corrected | 10/28/2020 | HENRY BAGHDASSARIAN |
| Permit Finaled | 10/28/2020 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/19/2018 | RICARDO RAMIREZ |
| "Q" conditions | Cleared | 11/26/2018 | SARAH GOLDMAN |
| CPC | Cleared | 11/26/2018 | SARAH GOLDMAN |
| CPC | Cleared | 11/26/2018 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/26/2018 | HISASHI KOBAYAKAWA |
| Supp. Use District POD/CDO/TDO | Cleared | 11/27/2018 | JEANALEE OBERGFELL |
| CPC | Cleared | 11/28/2018 | STEVEN WECHSLER |
| Green Code | Cleared | 12/6/2018 | RICARDO RAMIREZ |
| ZI | Cleared | 12/11/2018 | JEANALEE OBERGFELL |
| Specific Plan | Cleared | 1/22/2019 | PEDRO AYALA |
Contact Information
| Contractor | Ace Construction Inc; Lic. No.: 809243-B | 11921 SHERMAN WAY NORTH HOLLYWOOD, CA 91605 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2019 | Approved | JASON BORUTA |
| Footing/Foundation/Slab | 3/21/2019 | Approved | JOHN DODGE |
| Structural Steel Frame | 3/21/2019 | Not Ready for Inspection | JOHN DODGE |
| Deputy Steel/Welding | 5/28/2019 | Conditional Approval | TONY HARTONO |
| Wood Frame | 5/28/2019 | Partial Inspection | TONY HARTONO |
| Wood Frame | 6/12/2019 | Partial Approval | JASON BORUTA |
| Wood Frame | 6/14/2019 | Partial Approval | JASON BORUTA |
| Light Gage Steel Frame | 7/3/2019 | Partial Approval | JASON BORUTA |
| Interior/Exterior Lathing | 7/18/2019 | Approved | JASON BORUTA |
| Light Gage Steel Frame | 8/2/2019 | Partial Approval | TONY HARTONO |
| Insulation | 8/14/2019 | Partial Approval | JASON BORUTA |
| T-Bar Ceiling | 8/16/2019 | Conditional Approval | JASON BORUTA |
| Drywall Nailing | 8/20/2019 | Partial Approval | JASON BORUTA |
| Drywall Nailing | 11/12/2019 | Approved | JASON BORUTA |
| Footing/Foundation/Slab | 12/11/2019 | Approved | JASON BORUTA |
| Final | 12/30/2019 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 12/30/2019 | Not Ready for Inspection | JEFF BYTHEWAY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2019 | SGSOV Approved | JEFF BYTHEWAY |
| Smoke Detectors | 12/30/2019 | Approved | JEFF BYTHEWAY |
| Final | 1/8/2020 | Conditional Approval | JASON BORUTA |
| Green Building Final | 1/8/2020 | Approved | JASON BORUTA |