1032 N ILIFF ST 90272

Certificate Information: 1032 N ILIFF ST 90272

Application / Permit
18016-30000-30354
Plan Check / Job No.
B18WL06048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to ADU and addition per AB494 and SB229
Permit Issued
Issued on 1/31/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2018 APPLICANT
Assigned to Plan Check Engineer 9/25/2018 KAVIAN REFAHI
Corrections Issued 9/25/2018 KAVIAN REFAHI
Plan Check Approved 1/31/2020 ALFREDO JARA
Issued 1/31/2020 LADBS
CofO in Progress 2/26/2024 ARAM AVEDISIAN
Permit Finaled 3/6/2024 DANIEL ORRANTE
CofO Issued 3/6/2024 DANIEL ORRANTE
Permit Finaled 3/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 4/24/2019 RIDWAN HARDY
Address approval Cleared 1/23/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/23/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 1/23/2020 DINAH GARIN
Sewer availability Cleared 1/23/2020 DINAH GARIN
Grading Pre-Inspection Cleared 1/31/2020 KIRK LINKLATER

Contact Information

Contractor Westside Home And Design Inc; Lic. No.: 1013166-B 23246 WINDOM STREET      WEST HILLS, CA 91304

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2020 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 3/6/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 3/24/2020 Corrections Issued DANNY TOLENTINO
Footing/Foundation/Slab 3/26/2020 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 5/15/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 5/15/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/28/2020 Corrections Issued DANNY TOLENTINO
Green Building Rough 5/28/2020 Not Ready for Inspection DANNY TOLENTINO
PLUMBING-Rough 7/29/2020 Approved JOHN KIDWELL
Wood Frame 7/29/2020 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 8/11/2020 Corrections Issued ROBERT SHELLY
Interior/Exterior Lathing 8/17/2020 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 9/3/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 9/3/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/16/2020 Approved JOHN KIDWELL
Wood Frame 9/16/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 9/30/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 9/30/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 9/30/2020 Partial Approval JOHN KIDWELL
Sewer 9/30/2020 Approved JOHN KIDWELL
Drywall Nailing 10/20/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/22/2021 Partial Approval JOHN KIDWELL
Shower Pan 1/22/2021 Approved JOHN KIDWELL
Pre-Inspection 7/15/2021 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 8/25/2021 Approved JOHN KIDWELL
Final 8/25/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 8/25/2021 Approved JOHN KIDWELL
Green Building Final 8/25/2021 Approved JOHN KIDWELL
Green Building Rough 8/25/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Approved JOHN KIDWELL
Smoke Detectors 8/25/2021 Approved JOHN KIDWELL
Final 11/9/2021 Not Ready for Inspection JOHN KIDWELL
Final 2/26/2024 OK to Issue CofO ARAM AVEDISIAN