771 E PICO BLVD 90021
Certificate Information: 771 E PICO BLVD 90021
- Application / Permit
- 18016-30000-29524
- Plan Check / Job No.
- B18WL05876
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Laundry
- Work Description
- Remove & replace fire damaged roof framing with (N) matching roof framing to (E) industrial laundry bldg. (no change of use and SF). Code enforcement "Comply with Department Order effective date 07/04/2019.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/28/2024
Permit Application Status History
| Submitted | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | TROY DEGUZMAN |
| Corrections Issued | 9/24/2018 | TROY DEGUZMAN |
| Quality Review Completed | 10/4/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/10/2018 | APPLICANT |
| Applicant returned to address corrections | 12/12/2018 | TROY DEGUZMAN |
| Plan Check Approved | 12/18/2018 | TROY DEGUZMAN |
| No Progress | 11/30/2020 | TROY DEGUZMAN |
| Disabled Access Plans Picked Up | 12/28/2020 | APPLICANT |
| Green Plans Picked Up | 1/28/2021 | APPLICANT |
| Plan Check Approved | 2/22/2021 | TROY DEGUZMAN |
| Issued | 2/24/2021 | APPLICANT |
| Permit Finaled | 6/28/2024 | LUIS CCAMACHO |
Permit Application Clearance Information
| "D" conditions | Cleared | 11/16/2018 | TREVOR MARTIN |
| ZI | Cleared | 11/16/2018 | TREVOR MARTIN |
| Project located in CRA area | Cleared | 11/20/2018 | JIM URQUHART |
| Green Code | Cleared | 12/6/2018 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 12/18/2018 | SOMKIAT SUPANYACHOTSKUL |
| Hydrant and Access approval | Cleared | 1/7/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ostowari,, Sohrab; Lic. No.: C41014 | 7012 HELMSDALE RD WEST HILLS, CA 91307 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 4/19/2023 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 9/20/2023 | Corrections Issued | ALAN MORELOS |
| Wood Frame | 10/3/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 5/23/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 5/23/2024 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV No Gas | LUIS CCAMACHO |
| Smoke Detectors | 5/23/2024 | Approved | LUIS CCAMACHO |
| Final | 6/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 6/28/2024 | Permit Finaled | LUIS CCAMACHO |