10695 W SOMMA WAY 90077
Certificate Information: 10695 W SOMMA WAY 90077
- Application / Permit
- 18016-30000-23839
- Plan Check / Job No.
- B18WL04876
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) 2 story garage and ALQ to ADU per AB494 and SB229.
- Permit Issued
- Issued on 3/21/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2018 | APPLICANT |
| Green Plans Picked Up | 8/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | MANUEL GARCIA |
| Corrections Issued | 8/27/2018 | MANUEL GARCIA |
| Quality Review Completed | 9/7/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/10/2018 | APPLICANT |
| Applicant returned to address corrections | 10/10/2018 | MANUEL GARCIA |
| Plan Check Approved | 10/18/2018 | MANUEL GARCIA |
| Issued | 3/21/2019 | LADBS |
| Permit Expired-Status Void | 9/20/2019 | ROBERT SHELLY |
| Re-Activate Permit | 10/31/2019 | VINCENT COTTON |
| CofO in Progress | 10/29/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| CofO Issued | 11/5/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2018 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 9/28/2018 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 9/28/2018 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 9/28/2018 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2018 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 9/28/2018 | JOHN CONNEALLY |
| Miscellaneous | Cleared | 9/28/2018 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 9/28/2018 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 9/28/2018 | SARAH GOLDMAN |
| Private street | Cleared | 9/28/2018 | SARAH GOLDMAN |
| Roof/Waste drainage to street | Cleared | 9/28/2018 | JAMES MORALEZ |
| Sewer availability | Cleared | 9/28/2018 | JAMES MORALEZ |
| Grading Pre-Inspection | Cleared | 10/10/2018 | MANUEL GARCIA |
| Green Code | Cleared | 10/16/2018 | RICHARD GARCIA |
Contact Information
| Contractor | A & S Constructors Inc; Lic. No.: 921776-B | 937 MIRA VALLE ST MONTEREY PARK, CA 91754 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/20/2019 | Corrections Issued | ROBERT SHELLY |
| Special/Order Compliance | 9/20/2019 | Permit Expired-Status Void | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 4/1/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 4/1/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 10/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 10/17/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 10/17/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 10/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 10/17/2024 | Approved | CHRISTOPHER WILSON |
| Final | 10/25/2024 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 10/25/2024 | Approved | CHRISTOPHER WILSON |
| Final | 10/28/2024 | OK to Issue CofO | CHRISTOPHER WILSON |