564-566 E RIALTO AVE 90291

Certificate Information: 564-566 E RIALTO AVE 90291

Application / Permit
18016-30000-15438
Plan Check / Job No.
B18WL03122
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) COVERED PATIO ADDITION AT 1ST FLOOR AND MAJOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING. CONVERT MEZZANINE TO STORY TO MAKE BUILDING 3 STORY. CONVERT ANOTHER (E) 1-STORY SFD TO ADU PER AB-494 & SB-229 WITH NEW ATTACHED TRELLISES AND ATTACH IT TO THE (E) 2-STORY SFD. "COMPLY WITH DEPARTMENT ORDER effective date 04/24/2013. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" AND "COMPLY WITH DEPARTMENT ORDER effective date 11/14/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/10/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 ERWIN PASCUA
Green Plans Picked Up 6/11/2018 APPLICANT
Corrections Issued 6/27/2018 ERWIN PASCUA
Quality Review Completed 7/6/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/17/2018 APPLICANT
Applicant returned to address corrections 7/20/2018 ERWIN PASCUA
Applicant returned to address corrections 9/27/2018 ERWIN PASCUA
Plan Check Approved 1/10/2019 ERWIN PASCUA
Issued 4/10/2019 LADBS
CofO in Progress 8/25/2022 RYAN BARNES
Permit Finaled 9/9/2022 BRUCE TODD
CofO Issued 9/9/2022 BRUCE TODD
Permit Finaled 9/9/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 7/25/2018 MICHAEL CASTILLO
Construction near power lines Cleared 7/25/2018 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 7/25/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 7/25/2018 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 7/25/2018 MICHAEL CASTILLO
Sewer availability Cleared 7/25/2018 MICHAEL CASTILLO
Miscellaneous Cleared 7/27/2018 NOAH MCCOY
Miscellaneous Cleared 7/27/2018 NOAH MCCOY
Specific Plan Cleared 7/27/2018 EDER ROMERO
Specific Plan Cleared 7/27/2018 EDER ROMERO
Green Code Cleared 8/7/2018 RICHARD GARCIA
Coastal Zone Cleared 11/30/2018 MARITZA PRZEKOP
ZA Case Cleared 11/30/2018 MARITZA PRZEKOP
ZI Cleared 11/30/2018 MARITZA PRZEKOP
Specific Plan Cleared 12/5/2018 JEFF KHAU
ZI Cleared 12/5/2018 JEFF KHAU

Contact Information

Architect , ; Lic. No.: C36173 1261 LOMBARD STREET      SAN FRANCISCO, CA
Contractor M J M Builders Incorporated; Lic. No.: 809159-B 5008 WEST JEFFERSON BLVD      LOS ANGELES, CA 90016
Engineer Niaki, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/30/2020 Conditional Approval JOHN MATTILLO
Footing/Foundation/Slab 1/30/2020 Partial Approval RYAN BARNES
METHANE-Barrier 1/30/2020 Not Ready for Inspection RYAN BARNES
METHANE-Subgrade 1/30/2020 Not Ready for Inspection RYAN BARNES
Deputy Drilled-In Anchors 2/13/2020 Approved RYAN BARNES
Footing/Foundation/Slab 2/18/2020 Partial Approval RYAN BARNES
METHANE-Barrier 2/18/2020 Approved RYAN BARNES
METHANE-Subgrade 2/18/2020 Approved RYAN BARNES
Footing/Foundation/Slab 3/19/2020 Partial Approval RYAN BARNES
Deputy Drilled-In Anchors 4/2/2020 Approved RYAN BARNES
Footing/Foundation/Slab 4/2/2020 Approved RYAN BARNES
Wood Frame 4/16/2020 Partial Approval RYAN BARNES
Deputy Drilled-In Anchors 9/10/2020 Conditional Approval RYAN BARNES
Wood Frame 10/1/2020 Partial Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Conditional Approval RYAN BARNES
ELECTRICAL-Rough 6/15/2021 Corrections Issued RYAN BARNES
ELECTRICAL-Rough 9/1/2021 Approved RYAN BARNES
PLUMBING-Rough 9/1/2021 Corrections Issued RYAN BARNES
BUILDING-Rough-Frame 9/2/2021 Approved RYAN BARNES
Green Building Rough 9/2/2021 Approved RYAN BARNES
HVAC-Rough 9/2/2021 Approved RYAN BARNES
METHANE-Rough 9/2/2021 Approved RYAN BARNES
Insulation 9/21/2021 Approved RYAN BARNES
PLUMBING-Rough 9/21/2021 Approved RYAN BARNES
Shower Pan 9/21/2021 Approved RYAN BARNES
Drywall Nailing 10/12/2021 Approved RYAN BARNES
Interior/Exterior Lathing 10/12/2021 Approved RYAN BARNES
ELECTRICAL-Final 11/18/2021 Conditional Approval RYAN BARNES
Service/Power Release 11/18/2021 Approved RYAN BARNES
Deputy Drilled-In Anchors 11/19/2021 Conditional Approval JOHN MATTILLO
Service/Power Release 11/24/2021 Approved RYAN BARNES
Excavation/Setback/Form/Re-Bar 5/18/2022 Corrections Issued MARIAN PODPORA
Excavation/Setback/Form/Re-Bar 5/24/2022 Approved RYAN BARNES
Gas Test 6/6/2022 Approved RYAN BARNES
ELECTRICAL-Final 7/20/2022 Corrections Issued RYAN BARNES
Final 7/20/2022 Corrections Issued RYAN BARNES
Green Building Final 7/20/2022 Approved RYAN BARNES
HVAC-Final 7/20/2022 Corrections Issued RYAN BARNES
PLUMBING-Final 7/20/2022 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Approved RYAN BARNES
Smoke Detectors 7/20/2022 Approved RYAN BARNES
ELECTRICAL-Final 7/26/2022 Approved RYAN BARNES
Final 7/26/2022 Conditional Approval RYAN BARNES
HVAC-Final 7/26/2022 Approved RYAN BARNES
PLUMBING-Final 7/26/2022 Approved RYAN BARNES