564-566 E RIALTO AVE 90291
Certificate Information: 564-566 E RIALTO AVE 90291
- Application / Permit
- 18016-30000-15438
- Plan Check / Job No.
- B18WL03122
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) COVERED PATIO ADDITION AT 1ST FLOOR AND MAJOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING. CONVERT MEZZANINE TO STORY TO MAKE BUILDING 3 STORY. CONVERT ANOTHER (E) 1-STORY SFD TO ADU PER AB-494 & SB-229 WITH NEW ATTACHED TRELLISES AND ATTACH IT TO THE (E) 2-STORY SFD. "COMPLY WITH DEPARTMENT ORDER effective date 04/24/2013. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" AND "COMPLY WITH DEPARTMENT ORDER effective date 11/14/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/10/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | ERWIN PASCUA |
| Green Plans Picked Up | 6/11/2018 | APPLICANT |
| Corrections Issued | 6/27/2018 | ERWIN PASCUA |
| Quality Review Completed | 7/6/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 7/17/2018 | APPLICANT |
| Applicant returned to address corrections | 7/20/2018 | ERWIN PASCUA |
| Applicant returned to address corrections | 9/27/2018 | ERWIN PASCUA |
| Plan Check Approved | 1/10/2019 | ERWIN PASCUA |
| Issued | 4/10/2019 | LADBS |
| CofO in Progress | 8/25/2022 | RYAN BARNES |
| Permit Finaled | 9/9/2022 | BRUCE TODD |
| CofO Issued | 9/9/2022 | BRUCE TODD |
| Permit Finaled | 9/9/2022 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2018 | MICHAEL CASTILLO |
| Construction near power lines | Cleared | 7/25/2018 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 7/25/2018 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 7/25/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 7/25/2018 | MICHAEL CASTILLO |
| Miscellaneous | Cleared | 7/27/2018 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/27/2018 | NOAH MCCOY |
| Specific Plan | Cleared | 7/27/2018 | EDER ROMERO |
| Specific Plan | Cleared | 7/27/2018 | EDER ROMERO |
| Green Code | Cleared | 8/7/2018 | RICHARD GARCIA |
| Coastal Zone | Cleared | 11/30/2018 | MARITZA PRZEKOP |
| ZA Case | Cleared | 11/30/2018 | MARITZA PRZEKOP |
| ZI | Cleared | 11/30/2018 | MARITZA PRZEKOP |
| Specific Plan | Cleared | 12/5/2018 | JEFF KHAU |
| ZI | Cleared | 12/5/2018 | JEFF KHAU |
Contact Information
| Architect | , ; Lic. No.: C36173 | 1261 LOMBARD STREET SAN FRANCISCO, CA |
| Contractor | M J M Builders Incorporated; Lic. No.: 809159-B | 5008 WEST JEFFERSON BLVD LOS ANGELES, CA 90016 |
| Engineer | Niaki, Neman; Lic. No.: C46030 | 1107 CALIFORNIA AVE #2 SANTA MONICA, CA 90403 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2020 | Conditional Approval | JOHN MATTILLO |
| Footing/Foundation/Slab | 1/30/2020 | Partial Approval | RYAN BARNES |
| METHANE-Barrier | 1/30/2020 | Not Ready for Inspection | RYAN BARNES |
| METHANE-Subgrade | 1/30/2020 | Not Ready for Inspection | RYAN BARNES |
| Deputy Drilled-In Anchors | 2/13/2020 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | RYAN BARNES |
| METHANE-Barrier | 2/18/2020 | Approved | RYAN BARNES |
| METHANE-Subgrade | 2/18/2020 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 3/19/2020 | Partial Approval | RYAN BARNES |
| Deputy Drilled-In Anchors | 4/2/2020 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 4/2/2020 | Approved | RYAN BARNES |
| Wood Frame | 4/16/2020 | Partial Approval | RYAN BARNES |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | RYAN BARNES |
| Wood Frame | 10/1/2020 | Partial Approval | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Conditional Approval | RYAN BARNES |
| ELECTRICAL-Rough | 6/15/2021 | Corrections Issued | RYAN BARNES |
| ELECTRICAL-Rough | 9/1/2021 | Approved | RYAN BARNES |
| PLUMBING-Rough | 9/1/2021 | Corrections Issued | RYAN BARNES |
| BUILDING-Rough-Frame | 9/2/2021 | Approved | RYAN BARNES |
| Green Building Rough | 9/2/2021 | Approved | RYAN BARNES |
| HVAC-Rough | 9/2/2021 | Approved | RYAN BARNES |
| METHANE-Rough | 9/2/2021 | Approved | RYAN BARNES |
| Insulation | 9/21/2021 | Approved | RYAN BARNES |
| PLUMBING-Rough | 9/21/2021 | Approved | RYAN BARNES |
| Shower Pan | 9/21/2021 | Approved | RYAN BARNES |
| Drywall Nailing | 10/12/2021 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 10/12/2021 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 11/18/2021 | Conditional Approval | RYAN BARNES |
| Service/Power Release | 11/18/2021 | Approved | RYAN BARNES |
| Deputy Drilled-In Anchors | 11/19/2021 | Conditional Approval | JOHN MATTILLO |
| Service/Power Release | 11/24/2021 | Approved | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Corrections Issued | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 5/24/2022 | Approved | RYAN BARNES |
| Gas Test | 6/6/2022 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 7/20/2022 | Corrections Issued | RYAN BARNES |
| Final | 7/20/2022 | Corrections Issued | RYAN BARNES |
| Green Building Final | 7/20/2022 | Approved | RYAN BARNES |
| HVAC-Final | 7/20/2022 | Corrections Issued | RYAN BARNES |
| PLUMBING-Final | 7/20/2022 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 7/20/2022 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 7/26/2022 | Approved | RYAN BARNES |
| Final | 7/26/2022 | Conditional Approval | RYAN BARNES |
| HVAC-Final | 7/26/2022 | Approved | RYAN BARNES |
| PLUMBING-Final | 7/26/2022 | Approved | RYAN BARNES |