941 E 2ND ST 90012

Certificate Information: 941 E 2ND ST 90012

Application / Permit
18016-30000-14960
Plan Check / Job No.
B18WL03009
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Converting a portion of lobby to new office space, removal walls in URM
Permit Issued
Issued on 6/8/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2018 APPLICANT
Disabled Access Plans Picked Up 5/29/2018 APPLICANT
Assigned to Plan Check Engineer 5/30/2018 MANUEL GARCIA
Corrections Issued 6/4/2018 MANUEL GARCIA
Quality Review Completed 6/15/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/16/2018 MANUEL GARCIA
Plan Check Approved 11/16/2018 MANUEL GARCIA
Building Plans Picked Up 6/5/2020 APPLICANT
Issued 6/8/2020 LADBS
CofO in Progress 9/13/2022 MARK FERRARI
Permit Finaled 9/28/2022 TED RIES
CofO Issued 9/28/2022 TED RIES
Permit Finaled 9/28/2022 TED RIES

Permit Application Clearance Information

DAS Clearance Cleared 11/14/2018 MANUEL GARCIA

Contact Information

Architect Kostic,, Vasa; Lic. No.: C10740 1827-10TH ST_#4      SANTA MONICA, CA 90404
Contractor Owner-Builder       ,
Engineer Nastarin,, Hooman; Lic. No.: C62199 554 S SAN VICNETE BLVD 202      LOS ANGELES, CA 90048

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/29/2021 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 12/1/2021 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 12/30/2021 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/31/2022 Not Ready for Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval MARK FERRARI
Special/Order Compliance 4/12/2022 Approved MARK FERRARI
Footing/Foundation/Slab 4/26/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 4/28/2022 Conditional Approval MARK FERRARI
Light Gage Steel Frame 6/10/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/1/2022 Approved MARK FERRARI
Final 8/4/2022 Not Ready for Inspection MARK FERRARI
METHANE-Final 8/4/2022 Approved MARK FERRARI
METHANE-Rough 8/4/2022 Approved MARK FERRARI
Reinforced Masonry Frame 8/4/2022 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Not Ready MARK FERRARI
Smoke Detectors 8/4/2022 Not Ready for Inspection MARK FERRARI
Final 9/13/2022 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Approved MARK FERRARI
Smoke Detectors 9/13/2022 Approved MARK FERRARI