220-222 E GRAND BLVD 90291
Certificate Information: 220-222 E GRAND BLVD 90291
- Application / Permit
- 18016-30000-06236
- Plan Check / Job No.
- B18WL01326
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) DUPLEX WITH ATTACHED 2-CAR GARAGE INTO A DUPLEX WITH ATTACHED ONE-CAR GARAGE TO EXTEND THE BACK UNIT.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 5/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2018 | BRYAN OSORIO |
| Corrections Issued | 2/28/2018 | BRYAN OSORIO |
| Applicant returned to address corrections | 7/25/2018 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 12/24/2019 | MANUEL GARCIA |
| Issued | 12/22/2020 | APPLICANT |
| Permit Finaled | 5/9/2024 | CLAUDIO MORENO |
| CofO Issued | 5/9/2024 | CLAUDIO MORENO |
| Permit Finaled | 5/9/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2018 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 2/28/2018 | OSCAR GUTIERREZ |
| ZI | Cleared | 3/6/2018 | LAMBERT GIESSINGER |
| Specific Plan | Cleared | 7/3/2018 | JEFF KHAU |
| Specific Plan | Cleared | 7/12/2018 | EDER ROMERO |
| Coastal Zone | Cleared | 12/24/2019 | NOAH MCCOY |
Contact Information
| Architect | , ; Lic. No.: C27697 | , |
| Contractor | Freemodel Inc; Lic. No.: 1066986-B | 141 CLARENDON ROAD BURLINGAME, CA 94010 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2021 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 2/11/2021 | Approved | RYAN BARNES |
| Deputy Drilled-In Anchors | 2/16/2021 | Approved | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Not Ready for Inspection | RYAN BARNES |
| Insulation | 2/19/2021 | Approved | RYAN BARNES |
| METHANE-Rough | 2/19/2021 | Approved | RYAN BARNES |
| Wood Frame | 2/19/2021 | Partial Approval | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | MARIAN PODPORA |
| Drywall Nailing | 3/15/2021 | Approved | RYAN BARNES |
| Final | 4/26/2021 | Conditional Approval | RYAN BARNES |
| Smoke Detectors | 4/26/2021 | Approved | RYAN BARNES |
| Wood Frame | 4/26/2021 | Approved | RYAN BARNES |