513 W 103RD ST 90044

Certificate Information: 513 W 103RD ST 90044

Application / Permit
18016-20001-37612
Plan Check / Job No.
B19VN17037
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENT TO 18016-20000-37612 TO REVISE SCOPE OF WORK TO NEW 14' X 26'6" DETACHED ACCESSORY DWELLLING UNIT AS PER AB 494 AND SB 229 WITH 11' X 22' ATTACHED ONE CAR GARAGE , ALL WORK PER WFPP - SEE COMMENTS
Permit Issued
Issued on 12/10/2019
Issuing Office
Valley
Current Status
Permit Finaled on 8/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 RARES BODEA
Corrections Issued 10/20/2019 RARES BODEA
Quality Review Completed 10/22/2019 GUANG MIN TUNG
Building Plans Picked Up 10/22/2019 APPLICANT
Plan Check Approved 12/4/2019 RARES BODEA
Issued 12/10/2019 LADBS
Permit Finaled 8/11/2020 EUGENE CASSIDY

Permit Application Clearance Information

Green Code Cleared 10/22/2019 AARON COSTA
Address approval Cleared 11/1/2019 GUILLERMO PETRA
Construction near power lines Cleared 12/2/2019 OSCAR CASTRO
Low Impact Development Cleared 12/2/2019 ORVAL HERNANDEZ-MARCIAL
Eng Process Fee Ord 176,300 Cleared 12/3/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/3/2019 ADRIAN CASTRO
Sewer availability Cleared 12/3/2019 ADRIAN CASTRO

Contact Information

Contractor Treeium Inc; Lic. No.: 617148-B 5352 LAUREL CANYON BLVD #200      VALLEY VILLAGE, CA 91607

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/2/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 1/2/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 1/13/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 1/13/2020 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 1/27/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 1/27/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/29/2020 Approved EUGENE CASSIDY
Underground Mechanical 1/29/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/18/2020 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 3/18/2020 Approved JOHN KLARIN
Green Building Rough 3/18/2020 Approved JOHN KLARIN
HVAC-Rough 3/18/2020 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 3/18/2020 Approved JOHN KLARIN
PLUMBING-Rough 3/18/2020 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/18/2020 Approved JOHN KLARIN
HVAC-Rough 4/16/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 4/17/2020 Approved EUGENE CASSIDY
Insulation 4/27/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/27/2020 Partial Approval BRIAN CHRISTIAN
Drywall Nailing 5/4/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 6/22/2020 Approved EUGENE CASSIDY
Green Building Final 6/22/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 6/22/2020 Approved EUGENE CASSIDY
PLUMBING-Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/22/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/4/2020 Not Ready for Inspection EUGENE CASSIDY
Final 8/4/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 8/4/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 8/4/2020 Approved EUGENE CASSIDY
PLUMBING-Final 8/4/2020 Approved EUGENE CASSIDY
Service/Power Release 8/4/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/11/2020 Approved EUGENE CASSIDY
Final 8/11/2020 Permit Finaled EUGENE CASSIDY
Green Building Final 8/11/2020 Approved EUGENE CASSIDY
HVAC-Final 8/11/2020 Approved EUGENE CASSIDY
Service/Power Release 8/11/2020 Approved EUGENE CASSIDY