1421 S BARRY AVE #1-9 90025
Certificate Information: 1421 S BARRY AVE #1-9 90025
- Application / Permit
- 18016-20001-26489
- Plan Check / Job No.
- B19VN19267
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL PERMIT FOR 18016-20000-26489 FOR FULL SEISMIC UPGRADE & REPLACE (6) STANDARD PARKING STALLS WITH (6) COMPACT STALLS
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/18/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/21/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/25/2019 | APPLICANT |
| Plan Check Approved | 12/23/2019 | NILOOFAR MEHRAIN |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 4/6/2022 | JOHN DODGE |
| Permit Finaled | 4/18/2022 | DAVID TSAU |
| CofO Issued | 4/18/2022 | DAVID TSAU |
| Permit Finaled | 4/18/2022 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/23/2019 | DAISY BENICIA |
| Miscellaneous | Cleared | 12/23/2019 | NILOOFAR MEHRAIN |
| ZI | Cleared | 12/23/2019 | DAISY BENICIA |
Contact Information
| Contractor | M A S Construction Group Inc; Lic. No.: 1014814-B | 1543 7TH STREET SUITE 100 SANTA MONICA, CA 90401 |
| Engineer | Mulla,, Hasan_Ali Muhammad; Lic. No.: S1928 | 18643 TULSA ST NORTHRIDGE, CA 91324 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/10/2020 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 1/15/2020 | Partial Approval | JOHN DODGE |
| Pre-Inspection | 1/17/2020 | Partial Inspection | JOHN DODGE |
| Deputy Drilled-In Anchors | 1/30/2020 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 2/4/2020 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 11/20/2020 | Partial Approval | JOHN DODGE |
| Final | 2/22/2022 | Conditional Approval | GRANT WOODS |
| Smoke Detectors | 2/22/2022 | Approved | GRANT WOODS |
| Wood Frame | 2/22/2022 | Approved | GRANT WOODS |
| Final | 2/28/2022 | Conditional Approval | JOHN DODGE |
| Final | 3/2/2022 | Conditional Approval | JOHN DODGE |
| Final | 4/6/2022 | OK to Issue CofO | JOHN DODGE |