11148 N TELFAIR AVE 91331
Certificate Information: 11148 N TELFAIR AVE 91331
- Application / Permit
- 18016-20000-41141
- Plan Check / Job No.
- B18VN22171
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REPAIR (E) FIRE DAMAGED SFD 20% (INSPECTOR TO VERIFY) TO REPLACE FRAMING AT (E) BEDROOMS. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/29/2020
Permit Application Status History
| Submitted | 12/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 12/27/2018 | RAPHAEL ROSAS |
| Issued | 1/8/2020 | LADBS |
| Permit Finaled | 10/29/2020 | MICHEL ABAJAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | 610 ILEX STREET SAN FERNANDO, CA 91340 |
| Engineer | Carrillo,, Kiyoshi J; Lic. No.: C83472 | 8833 LANKERSHIM BLVD SUN VALLEY, CA 91352 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2020 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/2/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/5/2020 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 3/5/2020 | Approved | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 7/29/2020 | No Access for Inspection | DANIEL ORRANTE |
| HVAC-Rough | 7/29/2020 | No Access for Inspection | DANIEL ORRANTE |
| PLUMBING-Rough | 7/29/2020 | No Access for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 7/31/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/24/2020 | Approved | MICHEL ABAJAN |
| Insulation | 9/24/2020 | Approved | MICHEL ABAJAN |
| Final | 10/29/2020 | Permit Finaled | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2020 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 10/29/2020 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/29/2020 | Approved | MICHEL ABAJAN |