6227 N CARPENTER AVE 91606
Certificate Information: 6227 N CARPENTER AVE 91606
- Application / Permit
- 18016-20000-41013
- Plan Check / Job No.
- B18VN22094
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2018 | JEROME MAGAT PALMA |
| Corrections Issued | 12/27/2018 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/10/2019 | APPLICANT |
| Plan Check Approved | 1/18/2019 | JEROME MAGAT PALMA |
| Issued | 1/23/2019 | LADBS |
| CofO in Progress | 12/5/2024 | RAUL OLAGI |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
| CofO Issued | 12/15/2024 | RUBEN SALAS |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2019 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2019 | KAYLA PEJI |
| Sewer availability | Cleared | 1/14/2019 | KAYLA PEJI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/20/2023 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 11/1/2023 | Partial Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 12/13/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/13/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/27/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/27/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 12/27/2023 | Corrections Issued | JOHN HAYES |
| Final | 1/3/2024 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 1/3/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 1/24/2024 | Approved | JOHN COLEMAN |
| HVAC-Final | 1/24/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 8/21/2024 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Final | 8/21/2024 | Approved | ROBERT GOLD |
| Final | 8/21/2024 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 8/21/2024 | Approved | ROBERT GOLD |
| Green Building Rough | 8/21/2024 | Approved | ROBERT GOLD |
| HVAC-Final | 8/21/2024 | Approved | ROBERT GOLD |
| PLUMBING-Final | 8/21/2024 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 8/21/2024 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | ROBERT GOLD |
| Final | 9/25/2024 | Corrections Issued | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 9/25/2024 | Not Ready for Inspection | ROBERT GOLD |
| Final | 12/4/2024 | OK to Issue CofO | RAUL OLAGI |
| Smoke Detectors | 12/4/2024 | Approved | RAUL OLAGI |