6896 N PETIT AVE 91406
Certificate Information: 6896 N PETIT AVE 91406
- Application / Permit
- 18016-20000-40853
- Plan Check / Job No.
- B18VN21989
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE & REC. ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 6/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | JENNIFER LEE |
| Corrections Issued | 1/3/2019 | JENNIFER LEE |
| Plan Check Approved | 6/3/2019 | ANGELICA MARTINEZ |
| Issued | 6/3/2019 | LADBS |
| CofO in Progress | 12/30/2022 | RAUL OLAGI |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Miscellaneous | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2019 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 5/17/2019 | RIDWAN HARDY |
| Hold | Cleared | 6/19/2019 | LOURDES RAMIRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2019 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/15/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 9/15/2020 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 9/15/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 9/15/2020 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 10/5/2021 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/8/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/8/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/8/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | RAUL OLAGI |
| FLOOD-Proofing Certificate | 5/11/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/11/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | RAUL OLAGI |
| Shower Pan | 5/11/2022 | Approved | RAUL OLAGI |
| Insulation | 5/19/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/19/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 12/29/2022 | Approved | RAUL OLAGI |
| Final | 12/29/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 12/29/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/29/2022 | Approved | RAUL OLAGI |