225 W 85TH PL 90003

Certificate Information: 225 W 85TH PL 90003

Application / Permit
18016-20000-40497
Plan Check / Job No.
B18VN21754
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) (20'-6" x 26'-6") DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP
Permit Issued
Issued on 2/11/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2018 APPLICANT
Assigned to Plan Check Engineer 12/19/2018 MARVEL DELACRUZ
Corrections Issued 12/19/2018 MARVEL DELACRUZ
Applicant returned to address corrections 1/24/2019 JOHNNY WU
Applicant returned to address corrections 1/29/2019 RAPHAEL ROSAS
Plan Check Approved 2/11/2019 NIKTA MOUSAVI
Issued 2/11/2019 LADBS
CofO in Progress 8/6/2024 MICHAEL LEWIS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

"Q" conditions Cleared 1/18/2019 SHEILA GERSHON
Address approval Cleared 1/18/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/18/2019 JOHN LIN
Sewer availability Cleared 1/18/2019 JOHN LIN
ZI Cleared 1/18/2019 SHEILA GERSHON
Project located in CRA area Cleared 1/22/2019 JIM URQUHART

Contact Information

Contractor Boss Solar Inc; Lic. No.: 1032627-C46 20177 CORONA ST      CORONA, CA 92881

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2019 Corrections Issued WILLIAM ROSE
PLUMBING-Rough 3/28/2019 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 4/2/2019 Approved WILLIAM ROSE
Sewer 4/2/2019 Approved WILLIAM ROSE
BUILDING-Rough-Frame 5/23/2019 Corrections Issued WILLIAM ROSE
ELECTRICAL-Rough 5/23/2019 Corrections Issued WILLIAM ROSE
Green Building Rough 5/23/2019 Corrections Issued WILLIAM ROSE
PLUMBING-Final 5/23/2019 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 12/30/2019 Corrections Issued WILLIAM ROSE
ELECTRICAL-Rough 12/30/2019 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 12/30/2019 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 1/24/2020 Corrections Issued WILLIAM ROSE
Final 1/24/2020 Not Ready for Inspection WILLIAM ROSE
Green Building Final 1/24/2020 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 1/24/2020 Not Ready for Inspection WILLIAM ROSE
SGSOV-Seismic Gas S/O Valve 1/24/2020 SGSOV Not Ready WILLIAM ROSE
Smoke Detectors 1/24/2020 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 3/4/2020 Not Ready for Inspection WILLIAM ROSE
Final 3/4/2020 Not Ready for Inspection WILLIAM ROSE
Green Building Final 3/4/2020 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 3/4/2020 Not Ready for Inspection WILLIAM ROSE
Rough-Elec/Plmb/HVAC 3/4/2020 Corrections Issued WILLIAM ROSE
SGSOV-Seismic Gas S/O Valve 3/4/2020 SGSOV Not Ready WILLIAM ROSE
Smoke Detectors 3/4/2020 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 3/18/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 3/18/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 3/18/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 3/18/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 6/10/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 6/10/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 6/29/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 6/29/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 6/29/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/24/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/24/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 7/24/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/5/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 8/5/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 8/7/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 9/1/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/1/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 9/1/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/15/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/15/2020 Approved EUGENE CASSIDY
Insulation 9/15/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/28/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/28/2020 Approved EUGENE CASSIDY
Drywall Nailing 10/6/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 10/6/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/18/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 11/18/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 12/1/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 12/14/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 12/22/2020 Corrections Issued EUGENE CASSIDY
Final 2/2/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 2/19/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 3/1/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/12/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 8/23/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 5/7/2024 Partial Inspection MICHAEL LEWIS
Smoke Detectors 5/7/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 7/8/2024 Corrections Issued ANTHONY EGSON
Final 7/8/2024 Corrections Issued ANTHONY EGSON
Green Building Final 7/8/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 7/8/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 7/8/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 7/8/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 7/31/2024 Partial Approval MICHAEL LEWIS
Final 7/31/2024 Conditional Approval MICHAEL LEWIS
Green Building Final 7/31/2024 Approved MICHAEL LEWIS
HVAC-Final 7/31/2024 Approved MICHAEL LEWIS
PLUMBING-Final 7/31/2024 Approved MICHAEL LEWIS
Final 8/2/2024 OK to Issue CofO MICHAEL LEWIS