7507 N SIMPSON AVE 91605
Certificate Information: 7507 N SIMPSON AVE 91605
- Application / Permit
- 18016-20000-40458
- Plan Check / Job No.
- B18VN21722
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- MODIFY FOUR 1ST FLOOR UNITS TO ACCESSIBLE UNITS AND TWO 1ST FLOOR UNITS TO COMMUNICATION UNITS IN (E) 31 UNIT APT. Work also includes to alter window location/size, add new entry doors, re-roofing, modify parking layout to accommodate accessible parking spaces and provide eight bicycle parking for the replacement of two automobile parking spaces.
- Permit Issued
- Issued on 8/2/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Green Plans Picked Up | 1/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 1/23/2019 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/24/2019 | TIEN JEN WANG |
| Disabled Access Plans Picked Up | 1/24/2019 | APPLICANT |
| Building Plans Picked Up | 1/29/2019 | APPLICANT |
| Plan Check Approved | 6/20/2019 | ARSALAN SHABESTARI |
| Issued | 8/2/2019 | LADBS |
| CofO in Progress | 4/4/2022 | ROBERT DAVIS |
| Permit Finaled | 4/8/2022 | JEFFREY DURAN |
| CofO Issued | 4/8/2022 | JEFFREY DURAN |
| Permit Finaled | 4/8/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 3/14/2019 | DAVID MATSON |
| DAS Clearance | Cleared | 3/26/2019 | NORLITO MEDRANO |
| Housing rent stabilization | Cleared | 6/18/2019 | STEVEN HOFSTAD |
Contact Information
| Architect | Depanian,, Diran; Lic. No.: C16812 | 3663 LOS FELIZ BLVD # 5 LOS ANGELES, CA 90027 |
| Contractor | Precision General Commercial Contractors Inc; Lic. No.: 790153-B | 300 TURNEY ST 2ND FL SAUSALITO, CA 94965 |
| Engineer | Schulz,, Les Eric; Lic. No.: S2570 | 346 N LIMA SIERRA MADRE, CA 91024 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 1/24/2020 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 1/24/2020 | Partial Approval | ROBERT DAVIS |
| Insulation | 1/29/2020 | Approved | ROBERT DAVIS |
| Wood Frame | 1/29/2020 | Approved | ROBERT DAVIS |
| Drywall Nailing | 2/3/2020 | Approved | ROBERT DAVIS |
| Drywall Nailing | 2/7/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 2/10/2020 | Conditional Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 4/23/2020 | Approved | ROBERT DAVIS |
| Pre-Inspection | 5/7/2020 | Partial Inspection | ROBERT DAVIS |
| Final | 9/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 9/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Not Ready | ROBERT DAVIS |
| Smoke Detectors | 9/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 11/20/2020 | Conditional Approval | JEFFREY DURAN |
| Final | 6/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 6/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 6/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 6/10/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 6/10/2021 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 6/10/2021 | Approved | ROBERT DAVIS |
| Deputy Steel/Welding | 6/11/2021 | Conditional Approval | JEFFREY DURAN |
| Final | 6/14/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Insulation | 6/30/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 6/30/2021 | Conditional Approval | ROBERT DAVIS |
| Wood Frame | 7/14/2021 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 7/26/2021 | Partial Approval | ROBERT DAVIS |
| Final | 8/13/2021 | OK to Issue CofO | ROBERT DAVIS |