1735 S CARMELINA AVE 90025

Certificate Information: 1735 S CARMELINA AVE 90025

Application / Permit
18016-20000-40191
Plan Check / Job No.
B18VN21527
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC WALK IN: CONVERT THE (E) GARAGE AND STORAGE INTO A (N) ADU PER AB 494 AND SB 229 FOR ACCESSORY DWELLING UNITS. ALL WORK PER ENGINEER
Permit Issued
Issued on 12/19/2018
Issuing Office
Valley
Current Status
CofO Issued on 8/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2018 APPLICANT
Assigned to Plan Check Engineer 12/17/2018 MARVEL DELACRUZ
Corrections Issued 12/17/2018 MARVEL DELACRUZ
Plan Check Approved 12/19/2018 VLADIMIR ARUTYUNYAN
Issued 12/19/2018 LADBS
CofO in Progress 8/11/2020 KENNETH NAGLE
CofO Issued 8/12/2020 VINCENT COTTON
Permit Finaled 8/12/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 12/17/2018 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/17/2018 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 12/17/2018 HERMINIGILDO AGUSTIN
Sewer availability Cleared 12/17/2018 APEKSHYA BAJRACHARYA
Specific Plan Cleared 12/18/2018 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/4/2019 Conditional Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/16/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/16/2019 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/16/2019 Approved OGANES TARAKHCHYAN
Green Building Rough 9/16/2019 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/17/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 10/17/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 10/17/2019 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/4/2019 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/4/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 11/4/2019 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/8/2019 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/9/2019 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/9/2019 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 12/9/2019 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/9/2019 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/9/2019 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 12/17/2019 Approved OGANES TARAKHCHYAN
Insulation 12/20/2019 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/20/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/23/2019 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 1/6/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/6/2020 Approved OGANES TARAKHCHYAN
Shower Pan 1/8/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/31/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/3/2020 Approved OGANES TARAKHCHYAN
Final 4/3/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/3/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/3/2020 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 4/3/2020 Approved OGANES TARAKHCHYAN
Final 4/16/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/27/2020 Partial Approval OGANES TARAKHCHYAN
Final 5/26/2020 Partial Approval OGANES TARAKHCHYAN