1214 S ABBOT KINNEY BLVD 90291
Certificate Information: 1214 S ABBOT KINNEY BLVD 90291
- Application / Permit
- 18016-20000-39509
- Plan Check / Job No.
- B18VN21156
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (27) Artist-in-Residence
- Work Description
- Change of Use from (e) 3-story SFD (4,230 sf) to a Commercial Mixed-Use development ; Retail on ground floor (550 sf) ; Artist-In-Residence on 1st, 2nd, 3rd floor (2,990 sf) ; 3 onsite parking spaces (including 1 accessible stall) and 8 bicycle parking ; See comments
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/27/2018 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 12/28/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 1/2/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/2/2019 | APPLICANT |
| Applicant returned to address corrections | 6/28/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 9/20/2022 | REZA HAGHIGHAT |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | FARHAD DADBIN |
| Permit Finaled | 10/4/2023 | DAVID TSAU |
| CofO Issued | 10/4/2023 | DAVID TSAU |
| Permit Finaled | 10/4/2023 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 4/23/2019 | NORLITO MEDRANO |
| Address approval | Cleared | 9/4/2019 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/4/2019 | ANTHONY MAINEZ |
| ZA Case | Cleared | 3/4/2020 | LOUIS ORTEGA |
| ZA Case | Cleared | 3/4/2020 | LOUIS ORTEGA |
| Coastal Zone | Cleared | 3/9/2022 | NOAH MCCOY |
| ZA Case | Cleared | 3/9/2022 | NOAH MCCOY |
| ZA Case | Cleared | 3/9/2022 | NOAH MCCOY |
| Specific Plan | Cleared | 6/6/2022 | JAZMIN ROQUE |
| ZA Case | Cleared | 6/6/2022 | JAZMIN ROQUE |
| Specific Plan | Cleared | 9/20/2022 | FREDDY GARCIA |
Contact Information
| Architect | Rocha,, Carlos Joel; Lic. No.: C19775 | 28025 DOROTHY DRIVE SUITE 206 AGOURA HILLS, CA 91301 |
| Contractor | Dexterous Creative Contractors & Design Inc; Lic. No.: 1075451-B | 97 16TH ST APT E HERMOSA BEACH, CA 90254 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2023 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 2/16/2023 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 2/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 2/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 3/13/2023 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 3/29/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Drywall Nailing | 6/2/2023 | Partial Approval | FARHAD DADBIN |
| Insulation | 6/6/2023 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 6/6/2023 | Approved | FARHAD DADBIN |
| Drywall Nailing | 6/9/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 6/15/2023 | Approved | AMANUEL BERHE |
| Final | 8/16/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| METHANE-Final | 8/16/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| METHANE-Rough | 8/16/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 8/16/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 8/16/2023 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 9/28/2023 | Partial Approval | FARHAD DADBIN |
| METHANE-Final | 9/28/2023 | Approved | FARHAD DADBIN |
| METHANE-Rough | 9/28/2023 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 9/28/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 9/28/2023 | Approved | FARHAD DADBIN |
| Final | 10/2/2023 | OK to Issue CofO | FARHAD DADBIN |