17349-17351 W GRESHAM ST 91325

Certificate Information: 17349-17351 W GRESHAM ST 91325

Application / Permit
18016-20000-39435
Plan Check / Job No.
B18VN21129
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT IRREGULAR 12'-6" X 18'-11" PORTION OF (E) SFD AND 19'-10" X 20'-10" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, ADD 10'-0" X 10'-0" PATIO AND 20'-0" X 20'-0" 2-CAR GARAGE TO (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 9/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2018 APPLICANT
Assigned to Plan Check Engineer 12/10/2018 JENNIFER LEE
Corrections Issued 12/10/2018 JENNIFER LEE
Plan Check Approved 7/5/2019 RARES BODEA
Issued 9/5/2019 LADBS
CofO in Progress 12/13/2022 ROBERT GOLD
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/24/2019 CHRISTINE REUSCH
Eng Process Fee Ord 176,300 Cleared 1/24/2019 CHRISTINE REUSCH
Sewer availability Cleared 1/24/2019 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 7/5/2019 JULIUS GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/19/2019 Partial Approval JOHN HAYES
Footing/Foundation/Slab 9/19/2019 Partial Approval JOHN HAYES
Footing/Foundation/Slab 9/24/2019 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/11/2019 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 10/11/2019 Approved ARAM AVEDISIAN
Green Building Rough 10/11/2019 Approved ARAM AVEDISIAN
Drywall Nailing 10/30/2019 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2019 Corrections Issued MARK JOHNSON
Interior/Exterior Lathing 10/30/2019 Approved MARK JOHNSON
ELECTRICAL-Rough 7/30/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 7/30/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 7/30/2020 Corrections Issued MARK JOHNSON
Wood Frame 7/30/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 8/4/2020 Corrections Issued MARK JOHNSON
HVAC-Rough 8/4/2020 Corrections Issued MARK JOHNSON
PLUMBING-Rough 8/4/2020 Partial Approval MARK JOHNSON
Wood Frame 8/4/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 8/10/2020 Approved MARK JOHNSON
HVAC-Rough 8/10/2020 Approved MARK JOHNSON
PLUMBING-Rough 8/10/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 8/27/2020 Approved DANIEL ORRANTE
Wood Frame 8/27/2020 Approved DANIEL ORRANTE
Insulation 9/3/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/3/2020 Not Ready for Inspection MARK JOHNSON
Shower Pan 9/3/2020 Approved MARK JOHNSON
Drywall Nailing 9/8/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/8/2020 Approved MARK JOHNSON
ELECTRICAL-Final 11/4/2020 Approved MARK JOHNSON
Final 11/4/2020 Corrections Issued MARK JOHNSON
Green Building Final 11/4/2020 Approved MARK JOHNSON
HVAC-Final 11/4/2020 Approved MARK JOHNSON
PLUMBING-Final 11/4/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 11/4/2020 Approved MARK JOHNSON
Final 12/13/2022 OK to Issue CofO ROBERT GOLD