2928 E CESAR E CHAVEZ AVE 90033

Certificate Information: 2928 E CESAR E CHAVEZ AVE 90033

Application / Permit
18016-20000-37509
Plan Check / Job No.
B18VN20006
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Tenant improvement for (E) retail space unit 3 & 4. Change of use unit 5 from retail to medical clinic. Change of use unit 7 from retail to medical clinic and dental office.
Permit Issued
Issued on 2/1/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 12/4/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/5/2018 CHON CHIO KUO
Building Plans Picked Up 12/6/2018 APPLICANT
Disabled Access Plans Picked Up 12/6/2018 APPLICANT
Plan Check Approved 2/1/2019 VLADIMIR ARUTYUNYAN
Issued 2/1/2019 LADBS
CofO in Progress 6/12/2020 ERNESTO CORRAL
CofO in Progress 6/12/2020 ERNESTO CORRAL
Permit Finaled 6/12/2020 DAVID TSAU
CofO Issued 6/12/2020 DAVID TSAU
Permit Finaled 6/12/2020 DAVID TSAU

Permit Application Clearance Information

Project located in CRA area Cleared 12/11/2018 JIM URQUHART
ZA Case Cleared 12/11/2018 SHEILA GERSHON
ZA Case Cleared 12/11/2018 SHEILA GERSHON
ZA Case Cleared 12/11/2018 SHEILA GERSHON
ZA Case Cleared 12/11/2018 SHEILA GERSHON
Comm Cor/Mini-Mall Cleared 1/22/2019 HERMINIGILDO AGUSTIN
Comm Cor/Mini-Mall Cleared 1/22/2019 HERMINIGILDO AGUSTIN
DAS Clearance Cleared 1/31/2019 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 2/1/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/1/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Trig Builders Inc; Lic. No.: 1030887-B 6442 COLDWATER CANYON AVE 111      NORTH HOLLYWOOD, CA 91606

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/6/2019 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/8/2019 Corrections Issued JEFFREY FULTON
Wood Frame 3/28/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/10/2019 Partial Approval FELIX CEBALLOS
Wood Frame 10/21/2019 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/12/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/26/2019 Approved JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/16/2019 Partial Inspection JEFFREY FULTON
Final 5/14/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Final 5/14/2020 Approved RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Approved RONALD PACHECO
Smoke Detectors 5/14/2020 Not Ready for Inspection RONALD PACHECO
Final 5/19/2020 Not Ready for Inspection RONALD PACHECO
Smoke Detectors 5/19/2020 Not Ready for Inspection RONALD PACHECO
Final 5/27/2020 Conditional Approval RONALD PACHECO
Smoke Detectors 5/27/2020 Approved RONALD PACHECO
Final 6/12/2020 OK to Issue CofO ERNESTO CORRAL