1978-1978 1/2 S ESTRELLA AVE 1-2 90007

Certificate Information: 1978-1978 1/2 S ESTRELLA AVE 1-2 90007

Application / Permit
18016-20000-36772
Plan Check / Job No.
B18VN19602
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT GARAGE/ REC RM TO TWO FAMILY DWELLING
Permit Issued
Issued on 7/30/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 1/2/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/7/2019 CHON CHIO KUO
Building Plans Picked Up 1/10/2019 APPLICANT
Disabled Access Plans Picked Up 1/10/2019 APPLICANT
Green Plans Picked Up 1/10/2019 APPLICANT
Plan Check Approved 7/30/2019 VLADIMIR ARUTYUNYAN
Issued 7/30/2019 LADBS
CofO in Progress 2/19/2021 FREDDIE RIVERA
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 5/16/2019 RINA LARA
Address approval Cleared 5/16/2019 MARKOS PEREZ-BRAN
CPC Cleared 5/16/2019 RINA LARA
Eng Process Fee Ord 176,300 Cleared 5/20/2019 LEE GUILBEAUX
Sewer availability Cleared 5/20/2019 LEE GUILBEAUX
HPOZ Cleared 7/2/2019 MELISSA JONES
DAS Clearance Cleared 7/18/2019 OLLIE CARTER
Green Code Cleared 7/24/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2019 Approved PAUL BECKER
Pre-Inspection 8/9/2019 Partial Inspection JOAQUIN GREENOUGH
Insulation 9/4/2019 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/18/2019 Corrections Issued JOAQUIN GREENOUGH
Insulation 9/18/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 9/19/2019 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 9/26/2019 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/26/2019 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/7/2019 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 11/7/2019 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/13/2019 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 11/13/2019 Corrections Issued JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 11/18/2019 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 11/18/2019 Corrections Issued PAUL BECKER
ELECTRICAL-Rough 1/22/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 1/22/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 2/25/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 3/2/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 3/9/2020 Conditional Approval JOAQUIN GREENOUGH
HVAC-Rough 3/9/2020 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/18/2020 Not Ready for Inspection HORACE FULTZ
Green Building Rough 3/18/2020 Not Ready for Inspection HORACE FULTZ
MERV13>=Rough 3/18/2020 Not Ready for Inspection HORACE FULTZ
METHANE-Rough 3/18/2020 Partial Inspection HORACE FULTZ
BUILDING-Rough-Frame 4/1/2020 Corrections Issued DAVID CHAN
Gas Test 4/1/2020 Approved DAVID CHAN
Wood Frame 4/6/2020 No Access for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Partial Approval ROBERT VORHIS
Green Building Rough 4/9/2020 Not Ready for Inspection ROBERT VORHIS
MERV13>=Rough 4/9/2020 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 4/9/2020 Not Ready for Inspection ROBERT VORHIS
Insulation 5/18/2020 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/20/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 5/20/2020 Approved ROBERT MCDOWELL
Green Building Rough 5/20/2020 Approved ROBERT MCDOWELL
Insulation 5/20/2020 Approved ROBERT MCDOWELL
MERV13>=Rough 5/20/2020 Approved ROBERT MCDOWELL
METHANE-Rough 5/20/2020 Approved ROBERT MCDOWELL
Drywall Nailing 6/3/2020 Approved SABAS ALONSO
Final 7/20/2020 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Not Ready COREY HUPP
Smoke Detectors 7/20/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 8/4/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 8/4/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/4/2020 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Final 8/4/2020 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 8/4/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 8/6/2020 Approved ROBERT MCDOWELL
Final 8/6/2020 Conditional Approval ROBERT MCDOWELL
Green Building Final 8/6/2020 Approved ROBERT MCDOWELL
MERV13>=Final 8/6/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 8/6/2020 Approved ROBERT MCDOWELL
Final 2/18/2021 Not Ready for Inspection FREDDIE RIVERA