4926 N RUPERT AVE 91316

Certificate Information: 4926 N RUPERT AVE 91316

Application / Permit
18016-20000-34459
Plan Check / Job No.
B18VN18358
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 22'4" X 22'5" (E) GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229 AND ADD 22'4" X 25'5" ROOF DECK ABOVE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/30/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2018 APPLICANT
Assigned to Plan Check Engineer 10/24/2018 SARAH YOUSSEF
Corrections Issued 10/25/2018 SARAH YOUSSEF
Building Plans Picked Up 10/29/2018 APPLICANT
Applicant returned to address corrections 3/1/2019 JOHNNY WU
Plan Check Approved 4/12/2019 RARES BODEA
Plan Check Approved 5/30/2019 JEFFREY TANGONAN
Issued 5/30/2019 LADBS
CofO in Progress 5/20/2021 DAVID SANDOVAL
Permit Finaled 6/5/2021 MICHAEL SMITH
CofO Issued 6/5/2021 MICHAEL SMITH
Permit Finaled 6/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/6/2018 RUDY TERRIQUEZ.
Eng Process Fee Ord 176,300 Cleared 11/6/2018 RUDY TERRIQUEZ.
Sewer availability Cleared 11/6/2018 RUDY TERRIQUEZ.
Construction near power lines Cleared 2/11/2019 RIDWAN HARDY
Low Impact Development Cleared 2/28/2019 ANDRES COVARRUBIAS
Grading Pre-Inspection Cleared 3/1/2019 JOHNNY WU
Permit Cleared 3/1/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/1/2019 LEE GUILBEAUX
Trees in Parkway Cleared 3/18/2019 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 4/9/2019 ADRIAN SANCHEZ

Contact Information

Contractor Supreme Remodeling Inc; Lic. No.: 939981-B 14545 VICTORY BLVD UNIT 401      VAN NUYS, CA 91411
Engineer Yuzon,, Benigno S; Lic. No.: C38991 25531 PRADO DELASBELLOTAS      CALABASAS, CA 91302

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2019 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 7/2/2019 Not Ready for Inspection SEAN WIRCH
Green Building Rough 7/2/2019 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 7/2/2019 Partial Approval SEAN WIRCH
PLUMBING-Rough 8/13/2019 Approved SEAN WIRCH
Wood Frame 8/13/2019 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 8/20/2019 Not Ready for Inspection JOHN KIDWELL
Wood Frame 8/20/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 8/22/2019 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 8/22/2019 Approved SEAN WIRCH
Green Building Rough 8/22/2019 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 8/22/2019 Approved SEAN WIRCH
BUILDING-Rough-Frame 9/9/2019 Not Ready for Inspection SEAN WIRCH
Green Building Rough 9/9/2019 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 9/9/2019 Approved SEAN WIRCH
Wood Frame 9/9/2019 Approved SEAN WIRCH
Interior/Exterior Lathing 9/12/2019 Partial Approval SEAN WIRCH
Insulation 9/19/2019 Approved SEAN WIRCH
Footing/Foundation/Slab 10/18/2019 Corrections Issued SEAN WIRCH
Footing/Foundation/Slab 2/19/2020 Not Ready for Inspection RONALD COWAN
Shower Pan 3/5/2020 Approved DAVID SANDOVAL
ELECTRICAL-Final 11/9/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 4/9/2021 Approved DAVID SANDOVAL
Final 4/9/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 4/9/2021 Approved DAVID SANDOVAL
Green Building Final 4/9/2021 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 4/9/2021 Approved DAVID SANDOVAL
HVAC-Final 4/9/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 4/9/2021 Approved DAVID SANDOVAL
Final 4/27/2021 Conditional Approval RONALD COWAN
Green Building Final 4/27/2021 Approved RONALD COWAN
Final 5/20/2021 OK to Issue CofO DAVID SANDOVAL
Service/Power Release 5/20/2021 Approved DAVID SANDOVAL