14102 W TERRA BELLA ST 91331
Certificate Information: 14102 W TERRA BELLA ST 91331
- Application / Permit
- 18016-20000-33913
- Plan Check / Job No.
- B18VN18101
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER WFPP
- Permit Issued
- Issued on 11/15/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2018 | RAPHAEL ROSAS |
| Corrections Issued | 10/19/2018 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/23/2018 | APPLICANT |
| Plan Check Approved | 11/8/2018 | RAPHAEL ROSAS |
| Issued | 11/15/2018 | LADBS |
| CofO in Progress | 10/4/2024 | GREGG CUMMINGS |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2018 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 10/30/2018 | OSCAR CASTRO |
| Address approval | Cleared | 11/8/2018 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 11/8/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/8/2018 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Ochoa Victor Manuel; Lic. No.: 908306-B | 13700 FOOTHILL BLVD #920151 SYLMAR, CA 91342 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 1/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/23/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 11/23/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/5/2022 | No Access for Inspection | MATTHEW NELSON |
| Underground Mechanical | 1/3/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/17/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 3/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 3/17/2023 | Approved | GREGG CUMMINGS |
| Sewer | 3/17/2023 | Approved | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 6/8/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/19/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 7/19/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 11/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 11/30/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/13/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 12/20/2023 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/31/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 1/31/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/12/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 4/9/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/22/2024 | Approved | GREGG CUMMINGS |
| Insulation | 4/22/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/30/2024 | Approved | GREGG CUMMINGS |
| Insulation | 4/30/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 5/21/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/21/2024 | Approved | GREGG CUMMINGS |
| Green Building Final | 8/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 8/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/12/2024 | Corrections Issued | GREGG CUMMINGS |
| Final | 9/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/17/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 9/17/2024 | Approved | GREGG CUMMINGS |
| Final | 9/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/3/2024 | Approved | GREGG CUMMINGS |
| Final | 10/3/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 10/3/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/3/2024 | Approved | GREGG CUMMINGS |