19440 1/2 W HATTERAS ST 91356
Certificate Information: 19440 1/2 W HATTERAS ST 91356
- Application / Permit
- 18016-20000-31327
- Plan Check / Job No.
- B18VN16688
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20'-0" X 31'-4" PORTION OF (E) GARAGE/WORKSHOP TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, (E) 7'-2" X 20'-0" STORAGE AND 14'-4" X 38'-7" ATTACHED PATIO COVER TO REMAIN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/21/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2018 | JENNIFER LEE |
| Corrections Issued | 10/5/2018 | JENNIFER LEE |
| Plan Check Approved | 11/16/2018 | SARAH YOUSSEF |
| Issued | 12/21/2018 | LADBS |
| CofO in Progress | 8/5/2024 | JON MCHUGH |
| CofO Issued | 10/3/2024 | JOHN JANSON |
| Permit Finaled | 10/3/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/8/2018 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 11/8/2018 | RINA LARA |
| Address approval | Cleared | 11/16/2018 | RUDY TERRIQUEZ. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/20/2019 | Not Ready for Inspection | SEAN WIRCH |
| Pre-Inspection | 12/21/2023 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 1/10/2024 | Approved | JEFFREY PARD |
| Sewer | 1/10/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 2/8/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 2/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 2/8/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 2/8/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 2/15/2024 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 2/15/2024 | Approved | JON MCHUGH |
| Wood Frame | 2/27/2024 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 3/8/2024 | Not Ready for Inspection | HENRY KIM |
| Shower Pan | 3/8/2024 | Approved | HENRY KIM |
| Deputy Wood Construction | 3/11/2024 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 3/12/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 3/12/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/12/2024 | Approved | ALEXANDER HANDY |
| MERV13>=Rough | 3/12/2024 | Approved | ALEXANDER HANDY |
| Insulation | 3/14/2024 | Approved | HENRY KIM |
| Drywall Nailing | 3/21/2024 | Approved | ALEXANDER HANDY |
| Final | 6/20/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 6/20/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 7/26/2024 | Corrections Issued | JON MCHUGH |
| Final | 7/29/2024 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 7/29/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 8/5/2024 | Approved | JON MCHUGH |
| Final | 8/5/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 8/5/2024 | Approved | JON MCHUGH |
| HVAC-Final | 8/5/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 8/5/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 8/5/2024 | Approved | JON MCHUGH |