11100 W MAGNOLIA BLVD 91601
Certificate Information: 11100 W MAGNOLIA BLVD 91601
- Application / Permit
- 18016-20000-30785
- Plan Check / Job No.
- B18VN16388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE & OCCUPANCY FROM RETAIL TO RESTAURANT/BAR/RETAIL.
- Permit Issued
- Issued on 2/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | RUDOLF KINAR MELIKOFF |
| Disabled Access Plans Picked Up | 10/5/2018 | APPLICANT |
| Corrections Issued | 10/9/2018 | ABDUL CHEGENI |
| Quality Review Completed | 10/9/2018 | STEVEN KIM |
| Building Plans Picked Up | 10/11/2018 | APPLICANT |
| Applicant returned to address corrections | 2/11/2019 | ABDUL CHEGENI |
| Plan Check Approved | 2/20/2019 | ABDUL CHEGENI |
| Issued | 2/20/2019 | LADBS |
| CofO in Progress | 3/25/2022 | ROBERT DAVIS |
| Permit Finaled | 4/8/2022 | JEFFREY DURAN |
| CofO Issued | 4/8/2022 | JEFFREY DURAN |
| Permit Finaled | 4/8/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/8/2018 | ABDUL CHEGENI |
| Address approval | Cleared | 12/24/2018 | LEE GUILBEAUX |
| CPC | Cleared | 12/24/2018 | STEVEN WECHSLER |
| CPC | Cleared | 12/24/2018 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 12/24/2018 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Highway dedication | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Permit | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Permit | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 12/24/2018 | LEE GUILBEAUX |
| Project located in CRA area | Cleared | 12/26/2018 | JIM URQUHART |
| Food Service Establishment | Cleared | 1/24/2019 | RAMESHBHAIR PATEL |
| Green Code | Cleared | 1/25/2019 | ABDUL CHEGENI |
| Comm Cor/Mini-Mall | Cleared | 2/11/2019 | CLAUDE GOODING |
| Food establishment approval | Cleared | 2/11/2019 | LACDHS APPROVED |
| ZA Case | Cleared | 2/11/2019 | CLAUDE GOODING |
| Miscellaneous | Cleared | 2/13/2019 | CLAUDE GOODING |
Contact Information
| Architect | Grist, John Kenneth; Lic. No.: C4295 | 91 EAST GRAND VIEW AVENUE SIERRA MADRE, CA 91024 |
| Contractor | Heist Joseph Construction Inc; Lic. No.: 805106-B | P O BOX 1300 SIMI VALLEY, CA 930621300 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 4/9/2019 | SGSOV Not Ready | ROBERT DAVIS |
| Light Gage Steel Frame | 11/20/2019 | Corrections Issued | ANDREW DORSO |
| Light Gage Steel Frame | 11/21/2019 | No Access for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 11/26/2019 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 12/11/2019 | Approved | ROBERT DAVIS |
| Insulation | 2/18/2020 | No Access for Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 2/18/2020 | No Access for Inspection | ROBERT DAVIS |
| Insulation | 2/26/2020 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 2/26/2020 | Approved | ROBERT DAVIS |
| Drywall Nailing | 4/6/2020 | Approved | ROBERT DAVIS |
| Final | 4/6/2020 | Corrections Issued | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/6/2020 | SGSOV Not Ready | ROBERT DAVIS |
| Smoke Detectors | 4/6/2020 | Approved | ROBERT DAVIS |
| Wood Frame | 4/6/2020 | Approved | ROBERT DAVIS |
| Final | 6/9/2020 | No Access for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/9/2020 | SGSOV Not Ready | ROBERT DAVIS |
| Final | 6/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Approved | ROBERT DAVIS |
| Final | 12/8/2021 | No Access for Inspection | ROBERT DAVIS |
| Final | 3/10/2022 | Corrections Issued | ROBERT DAVIS |
| Final | 3/25/2022 | OK to Issue CofO | ROBERT DAVIS |
| Special/Order Compliance | 3/25/2022 | Approved | ROBERT DAVIS |