15347 W ROSCOE BLVD 91402
Certificate Information: 15347 W ROSCOE BLVD 91402
- Application / Permit
- 18016-20000-29662
- Plan Check / Job No.
- B18VN15791
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE: (20'-3" X 60'-0") (E) RESTAURANT TO (N) MINI-MARKET/RETAIL (FOR (E) GAS STATION)., RE-CONFIGURE & RE-STRIPE PARKING LOT [SEE COMMENTS]. "COMPLY WITH DEPARTMENT ORDER effective date 01/29/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | ALEXANDER SBARDELLATI |
| Disabled Access Plans Picked Up | 10/12/2018 | APPLICANT |
| Green Plans Picked Up | 10/12/2018 | APPLICANT |
| Corrections Issued | 10/22/2018 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 10/25/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 10/25/2018 | APPLICANT |
| Applicant returned to address corrections | 11/15/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/15/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/25/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/12/2019 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 4/10/2019 | ALEXANDER SBARDELLATI |
| No Progress | 3/18/2021 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 9/15/2021 | TROY DEGUZMAN |
| Issued | 10/19/2021 | APPLICANT |
| TCO Issued (Expire Date: 02-24-2026) | 8/28/2025 | JEFFREY DURAN |
| CofO in Progress | 1/28/2026 | ANDREW DORSO |
| Permit Finaled | 2/10/2026 | JEFFREY DURAN |
| CofO Issued | 2/10/2026 | JEFFREY DURAN |
| Permit Finaled | 2/10/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/3/2019 | RICK TORRES |
| Permit | Cleared | 1/3/2019 | KAYLA PEJI |
| ZI | Cleared | 1/3/2019 | RICK TORRES |
| ZI | Cleared | 1/3/2019 | RICK TORRES |
| Green Code | Cleared | 3/12/2019 | ALEXANDER SBARDELLATI |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2019 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 4/8/2019 | CHRISTINE REUSCH |
| DAS Clearance | Cleared | 5/20/2021 | NORLITO MEDRANO |
| Food Service Establishment | Cleared | 8/30/2021 | JASH PATEL |
| Food establishment approval | Cleared | 9/15/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2021 | Approved | BEHROUZ HASHEMI |
| Footing/Foundation/Slab | 11/21/2023 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 12/8/2023 | Approved | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/4/2024 | Approved | ANDREW DORSO |
| Wood Frame | 11/4/2024 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 11/19/2024 | Approved | ANDREW DORSO |
| Drywall Nailing | 12/9/2024 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 12/9/2024 | Approved | ANDREW DORSO |
| Final | 8/11/2025 | Partial Approval | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 8/11/2025 | Approved | ANDREW DORSO |
| Special/Order Compliance | 1/27/2026 | Conditional Approval | ANDREW DORSO |
| Final | 1/28/2026 | OK to Issue CofO | ANDREW DORSO |