340 S ANITA AVE 90049
Certificate Information: 340 S ANITA AVE 90049
- Application / Permit
- 18016-20000-28506
- Plan Check / Job No.
- B18VN15169
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) (18'-1"X 18'-5") REC. ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 . ADD SHOWER , KITCHEN, AND WASHER AND DRYER. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/12/2020
- Issuing Office
- Current Status
- CofO Issued on 8/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2018 | PINANK PATEL |
| Corrections Issued | 9/4/2018 | PINANK PATEL |
| Applicant returned to address corrections | 11/19/2018 | NIKTA MOUSAVI |
| Plan Check Approved | 11/27/2018 | RAPHAEL ROSAS |
| Issued | 8/12/2020 | APPLICANT |
| CofO in Progress | 8/4/2022 | ANDREW NAVE |
| CofO in Progress | 8/4/2022 | ANDREW NAVE |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
| CofO Issued | 8/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/27/2018 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Ross D Construction; Lic. No.: 871334-B | 22664 KITTRIDGE STREET WEST HILLS, CA 91307 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/17/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 9/17/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 9/17/2020 | Partial Approval | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 11/6/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/6/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/20/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/20/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/24/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/24/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/15/2020 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/15/2020 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/13/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/6/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/6/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/6/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/20/2021 | Corrections Issued | DANIEL ORRANTE |
| HVAC-Rough | 10/20/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| Footing/Foundation/Slab | 1/25/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 2/11/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/11/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 3/11/2022 | Approved | JOHN KIDWELL |
| Insulation | 3/11/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 3/11/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/16/2022 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 3/30/2022 | Approved | JOHN KIDWELL |
| Final | 7/19/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 7/19/2022 | Corrections Issued | ANDREW NAVE |
| Final | 7/28/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 7/28/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/1/2022 | OK to Issue CofO | ANDREW NAVE |
| Smoke Detectors | 8/1/2022 | Approved | ANDREW NAVE |