11100 W BLIX ST 91602

Certificate Information: 11100 W BLIX ST 91602

Application / Permit
18016-20000-23721
Plan Check / Job No.
B18VN12599
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 35'-0" X 42'-4" DETACHED 2-STORY STORAGE BUILDING TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 8/31/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2018 APPLICANT
Assigned to Plan Check Engineer 7/31/2018 JENNIFER LEE
Corrections Issued 7/31/2018 JENNIFER LEE
Plan Check Approved 8/30/2018 SARAH YOUSSEF
Issued 8/31/2018 LADBS
CofO in Progress 2/10/2022 ARAM AVEDISIAN
CofO Issued 3/10/2022 MICHAEL SMITH
Permit Finaled 3/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Hold Cleared 8/27/2018 LOURDES RAMIRO
Address approval Cleared 8/28/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 8/28/2018 JOHN LIN
Sewer availability Cleared 8/28/2018 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer German, Chatsky; Lic. No.: C84153       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/8/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 1/8/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 1/8/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 1/8/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 1/8/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 1/10/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 1/10/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 1/10/2020 Partial Inspection JEFFREY PARD
Pre-Inspection 1/10/2020 Partial Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 2/5/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/5/2020 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 2/5/2020 Approved JEFFREY PARD
Green Building Rough 2/5/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/5/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/12/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/12/2020 Corrections Issued JEFFREY PARD
Green Building Rough 2/12/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/12/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 2/12/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/19/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/19/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 2/19/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/19/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 2/19/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/28/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/28/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 2/28/2020 Approved JEFFREY PARD
Wood Frame 2/28/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 6/8/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 6/8/2020 Approved JEFFREY PARD
HVAC-Rough 6/8/2020 Approved JEFFREY PARD
Wood Frame 6/8/2020 Approved JEFFREY PARD
Insulation 6/12/2020 Not Ready for Inspection BRENDAN LOONEY
Sewer 6/12/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Corrections Issued DANIEL DREW
Insulation 6/15/2020 Approved DANIEL DREW
Shower Pan 6/15/2020 Approved DANIEL DREW
Sewer 6/17/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Not Ready for Inspection THOMAS FINNILA
Sewer 7/8/2020 Approved THOMAS FINNILA
Wood Frame 7/8/2020 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 8/17/2020 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/17/2020 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 8/27/2020 Partial Approval THOMAS FINNILA
Wood Frame 9/23/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/30/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 10/15/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 11/16/2020 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/16/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/13/2021 Corrections Issued JOHN HAYES
HVAC-Rough 5/13/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/13/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 5/20/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 5/20/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/20/2021 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 5/25/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Rough 5/26/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 5/26/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/26/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 6/7/2021 Approved GREGG CUMMINGS
HVAC-Rough 6/7/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 6/8/2021 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 6/10/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 7/1/2021 Partial Approval ARAM AVEDISIAN
Wood Frame 7/1/2021 Approved ARAM AVEDISIAN
Drywall Nailing 7/9/2021 Approved MICHEL ABAJAN
Shower Pan 7/9/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/2/2021 Partial Inspection THOMAS FINNILA
ELECTRICAL-Final 2/2/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/4/2022 Approved THOMAS FINNILA
Final 2/4/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 2/4/2022 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 2/4/2022 Approved THOMAS FINNILA
Final 2/10/2022 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 2/10/2022 Approved ARAM AVEDISIAN