7334 N REMMET AVE 91303
Certificate Information: 7334 N REMMET AVE 91303
- Application / Permit
- 18016-20000-23336
- Plan Check / Job No.
- B18VN12414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED STORAGE AND CARPORT TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229 AND ADDITION OF 295 SQ.FT. TO ENPAND THE NEW ADU. ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/11/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2018 | MARVEL DELACRUZ |
| Corrections Issued | 7/23/2018 | MARVEL DELACRUZ |
| Plan Check Approved | 8/24/2018 | JOHNNY WU |
| Issued | 9/11/2018 | LADBS |
| Refund in Progress | 9/3/2019 | MARY SUM |
| Refund Closed | 9/3/2019 | MARY SUM |
| Reactivate - Status Void | 9/3/2019 | MARY SUM |
| Refund in Progress | 9/16/2019 | CHRISTINA TABIRARA |
| Refund Denied | 4/29/2020 | CHRISTINA TABIRARA |
| CofO in Progress | 4/27/2021 | HENRY KIM |
| CofO Issued | 4/29/2021 | JOHN JANSON |
| Permit Finaled | 4/29/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/23/2018 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/24/2018 | EDUARDO PEDROZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2018 | No Access for Inspection | JOHN COLEMAN |
| Pre-Inspection | 9/25/2018 | Partial Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 2/27/2019 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 2/27/2019 | Not Ready for Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2019 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 2/27/2019 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 2/27/2019 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 8/13/2020 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 8/13/2020 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 8/24/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 8/24/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 9/8/2020 | Approved | HENRY KIM |
| Sewer | 9/8/2020 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 9/8/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 9/18/2020 | Corrections Issued | HENRY KIM |
| Sewer | 9/18/2020 | Approved | HENRY KIM |
| Underground Mechanical | 9/18/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 10/7/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 10/7/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/22/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 11/13/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 11/13/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 11/13/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 12/10/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 12/10/2020 | Not Ready for Inspection | HENRY KIM |
| Insulation | 12/10/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 12/18/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | HENRY KIM |
| Green Building Rough | 12/18/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 12/18/2020 | Approved | HENRY KIM |
| Drywall Nailing | 12/22/2020 | Approved | MARK JOHNSON |
| Shower Pan | 12/22/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 1/4/2021 | Approved | HENRY KIM |
| Special/Order Compliance | 1/14/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 3/17/2021 | Corrections Issued | HENRY KIM |
| Final | 3/17/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 3/17/2021 | Approved | HENRY KIM |
| HVAC-Final | 3/17/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 3/17/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 3/17/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 4/9/2021 | Approved | HENRY KIM |
| Final | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 4/9/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 4/9/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/9/2021 | SGSOV Not Ready | HENRY KIM |
| Final | 4/16/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 4/16/2021 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | HENRY KIM |
| Final | 4/27/2021 | OK to Issue CofO | HENRY KIM |